MahaRERA Property Intelligence · Thane

O22 Business Park

P51700053701 · Wagle Estate · promoter Midas Touch

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51700053701
Registered on22 Nov 2023
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Midas Touch is the promoter of record on 13 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Construction Progress

MahaRERA's cost filing puts construction at ~87.4% of the estimated project cost incurred as of the last certificate (₹160.22 Cr spent against a ₹183.42 Cr estimate). This financial % is the regulator's own proxy for how much is physically built — the closest public read on real progress, and one a brochure never shows.

Cost-incurred % as last certified to MahaRERA; it can lag on-site reality between filings. Confirm the current stage and the latest Form 2 before you book.

Sales & Inventory

Of 355 homes filed with MahaRERA, 185 are sold/booked (124 with registered agreements + 61 booked) and 170 remain available (~52% sold) — selling steadily. Buyers have committed ₹209.17 Cr in agreement value so far. Of that, ₹120.97 Cr (~58%) is already collected, ₹88.20 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 185 registered agreements, the effective carpet rate is ₹15,285/sqft (typical range ₹12,613–₹18,317) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+12 and 355 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
O22 Business Park1G+12355-

Unit mix on the filing: 355 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Wagle Estate, Road No 22, Thane, Thane, 400604. Per the filed land record, the plot is bounded to the north by Plot No a-112, to the south by Plot No A-120 Plot No A-113, to the east by Road and to the west by Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~10 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ11 km
Chhatrapati Shivaji Int'l Airport15 km
Bandra Kurla Complex (BKC)17 km
Lower Parel / Worli business district25 km
Nariman Point / Fort33 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Wagle Estate

Urban Villa
possession by Jul 2026 · Yash Infra
One Wagle
possession by Oct 2026 · Sagar Nirman Spaces
Bhairaav Milestone Phase II
possession by Dec 2026 · Sharpmind Consultancy Services Private L
Aura Business Center
possession by Dec 2026 · AUM Developers
Centura Square
possession by Dec 2026 · Supper Squarefeet Infraventures LLP
White Rose
possession by Dec 2026 · M/s Eeshan Enterprises

Other RERA-registered projects in Thane

OAK Leaf Towers
possession by Dec 2030 · Axis Housing Private Limited
Oasis Habitats
declared completion Jun 2026 · Faisal Nisar Ahmed Shaikh
Oasis Royale
declared completion Dec 2018 · Magestic Premises Private Limited
Obelia A
declared completion Dec 2022 · Roma Builders Private Limited
Obelia B
declared completion Dec 2022 · Roma Builders Private Limited
Oceanic
possession by Dec 2028 · Inder's Infra

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026