OASIS PHASE II PALM BUILDING

P52000006233 · NEAR CHHATRAPATI SHIVANJI CHOUK · promoter Abs Realtors

Certificate SignedDue 31 Jul 2022

Delivery & Registration

MahaRERA registrationP52000006233
Registered on14 Aug 2017
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 48 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
OASIS PHASE II PALMS BUILDING1G+5-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC1250369116/10/2025Yusuf Khalil vs ABS REALTORSorder passed

Location, Land & Connectivity

Located at NEAR CHHATRAPATI SHIVANJI CHOUK, CHOUNDI MAPGAON ROAD, Mumbai City, Mumbai City, 402201. Per the filed land record, the plot is bounded to the north by GUT NO 275 276, to the south by CHONDI TO MAPGAON ROAD, to the east by GAOTHAN and to the west by GUT NO 264 266. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort24 km
Lower Parel / Worli business district31 km
Bandra Kurla Complex (BKC)38 km
Chhatrapati Shivaji Int'l Airport41 km
Powai / Hiranandani business park44 km
Andheri MIDC / SEEPZ45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Alibag

Prajyot Devasthal
possession by Sep 2026 · Gaurav Pravin Gharat
Excellensea Villas Project
possession by Dec 2026 · Unicorp Realty Private Limited
Balibaug Rekreasi
possession by Dec 2026 · Pushpam Infra LLP
Ekaante Phase 3
possession by Dec 2026 · Green Park Developers
Lakshminarayan CO-OP Housing Society LTD Proposed
possession by Dec 2026 · Elnube Realtors PVT LTD
Sukh Shanti Residential Project
possession by Dec 2026 · SRS Developers

Major developers building in Alibag

Other RERA-registered projects in Raigarh

Obelisk
declared completion Mar 2025 · Shree Chinmay Gaurang Infrastructure
Ocaso Vaddo
possession by Mar 2029 · Sagaj Relators LLP
Ocean Heights
possession by Jun 2027 · H S Construction
Odhav Krupa
declared completion Dec 2023 · Rashmi Corporation
Olive Boulevard
possession by Dec 2029 · Olive Infra & Lifestyle LLP
Olympeo Neo City
possession by Dec 2027 · Priztine Infra LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026