OASIS PHASE II PALM BUILDING

NEAR CHHATRAPATI SHIVANJI CHOUK · ABS REALTORS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000006233

Delivery and registration

When is the project declared for completion?

OASIS PHASE II PALM BUILDING is registered with MahaRERA as P52000006233 and the promoter has declared completion for 31 Jul 2022.

31 Jul 2022

declared completion

50months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000006233
Registered on14 Aug 2017
Promoter-declared completion31 Jul 2022
Current statusCertificate Signed
Against todayabout 50 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OASIS PHASE II PALM BUILDING record 21 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 21 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OASIS PHASE II PALM BUILDING in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
OASIS PHASE II PALMS BUILDING1G+5-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for OASIS PHASE II PALM BUILDING, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250369116/10/2025Yusuf Khalil vs ABS REALTORSorder passed

Location, Land & Connectivity

Located at NEAR CHHATRAPATI SHIVANJI CHOUK, CHOUNDI MAPGAON ROAD, Mumbai City, Mumbai City, 402201. Per the filed land record, the plot is bounded to the north by GUT NO 275 276, to the south by CHONDI TO MAPGAON ROAD, to the east by GAOTHAN and to the west by GUT NO 264 266. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort24 km
Lower Parel / Worli business district31 km
Bandra Kurla Complex (BKC)38 km
Chhatrapati Shivaji Int'l Airport41 km
Powai / Hiranandani business park44 km
Andheri MIDC / SEEPZ45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Alibag

Excellensea Villas Project
possession by Dec 2026 · Unicorp Realty Private Limited
Balibaug Rekreasi
possession by Dec 2026 · Pushpam Infra LLP
Lakshminarayan CO-OP Housing Society LTD Proposed
possession by Dec 2026 · Elnube Realtors PVT LTD
Swastik Orchid
possession by Dec 2026 · Swastik Developers
Savitri Heritage
possession by Mar 2027 · Mukesh Bhoormal Jain
Shree Radha Krishna Residency
possession by May 2027 · Shree Radha Enterprises

Major developers building in Alibag

Other RERA-registered projects in Raigarh

Ocaso Vaddo
possession by Mar 2029 · Sagaj Relators LLP
Ocean Heights
possession by Jun 2027 · H S Construction
Olive Boulevard
possession by Dec 2029 · Olive Infra & Lifestyle LLP
Olive Paradise
declared completion Mar 2024 · S M Developers
Olympeo Neo City
possession by Dec 2027 · Priztine Infra LLP
Olympeo Retreat - Phase 1
declared completion Jun 2025 · Paradiso Realty Solutions LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026