Mumbai/Project record

MahaRERA · the public record

OM SHIKHAR

JUNI DOMBIVLI · VAIDIK DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Oct 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700029604

Delivery and registration

When is the project declared for completion?

OM SHIKHAR is registered with MahaRERA as P51700029604 and the promoter has declared completion for 30 Oct 2023.

30 Oct 2023

declared completion

35months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700029604
Registered on11 Jun 2021
Promoter-declared completion30 Oct 2023
Current statusCertificate Signed
Against todayabout 35 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for OM SHIKHAR record 11 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 11 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Vaidik Developers is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for OM SHIKHAR in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
OM SHIKHAR1G+701 May 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered01 May 2023Dear Sir, The captioned project which comprises of one building is about 80% complete. The proposed date of completion was 01.05.2022. However, we had put for revision in plan w
01 May 202330 Oct 2023The promoter has put an application for Occupancy Certificate with the concerned authority. Hence for the intervening period promoter requires an extension. Providing herewith cons

Location, Land & Connectivity

Located at JUNI DOMBIVLI, DIVA VASAI RAILWAY TRACK ROAD, Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by 6 M WIDE ROAD, to the south by S NO 6 H NO 4, to the east by S NO 15 and to the west by S NO 107 H NO 13. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~14 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park14 km
Andheri MIDC / SEEPZ15 km
Chhatrapati Shivaji Int'l Airport19 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district29 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel
Sumati Skyline
possession by Sep 2026 · Subhash Skyline Infra
Vinayak Prerana
possession by Sep 2026 · Nakshatra Group
Shanu Majestic
possession by Dec 2026 · Fortune Group Of Construction
Balaji Annex
possession by Dec 2026 · M/S OM Swayambhu Siddhivinayak Builders

Major developers building in Dombivli East

Other RERA-registered projects in Thane

OM Shiv Angan CHS
possession by Mar 2027 · Ritu Builders AND Developers
OM Shiv Ganesh CO Operative Housing Society LTD
possession by Mar 2027 · Impressions NXT
OM Shivanjali CHS LTD
possession by Oct 2027 · Gyandev Builders AND Developers
OM Shree CHS LTD
declared completion Sep 2022 · G K Builders
OM Shree Ganesh Chhaya CHS
declared completion Mar 2024 · Shree Ganesh Developers
OM Shree Vighnesh
declared completion Dec 2023 · M/S Trimurti Homes

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026