Om Shiv Matoshree SRA CHS LTD

DAHISAR · ARJUN ANANT WAGHMARE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800004827

Delivery and registration

When is the project declared for completion?

Om Shiv Matoshree SRA CHS LTD is registered with MahaRERA as P51800004827 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800004827
Registered on09 Aug 2017
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Om Shiv Matoshree SRA CHS LTD record 36 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Arjun Anant Waghmare is the promoter of record on 31 projects registered with MahaRERA, 6 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

31projects

registered with MahaRERA

6flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Om Shiv Matoshree SRA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+16.

BuildingWingsFloorsDeclared completion
Sai Krupa Mall and Tower1G+16-

Legal and disputes

What disputes are disclosed?

4 complaints are on the MahaRERA record for Om Shiv Matoshree SRA CHS LTD, with orders passed in 3 of them.

4complaints

3with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019835215/09/2021Suresh Thakar vs Arjun Anant Waghmareorder passed
CC00600000005748730/12/2018Avinash Ramteke vs Arjun waghmareorder passed
CC00600000020959301/01/2022MOHAN NARAYAN KOTHARI and SUSHILA MOHAN KOTHARI vs M/s. SUNIL CONSTRUCTIONSorder passed
CC1240030202/10/2024DEEPSHIKHA PRADEEP KULSHRESTHA vs ARJUN ANANT WAGHMAREpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Additional Deputy Collector Enc And Rem7742017Ongoing
Additional Deputy Collector Enc &Rem10275 of 20182018Ongoing

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 4 times, as recorded on the register.

FromExtended toStated reason
as registered30 May 2020delay in vacating the plot from tenents as the project is developed under sra scheme. matter went to the court and ultimately vacated in february 2019
30 May 202030 Nov 2021DUE TO CORONA EFFECT LABOUR PROBLEM AS WELL AS PASSING OFFICES ARE NOT WORKING AT FULL STRENGTH. WE ARE UNABLE TO GET REVISED OUR I.O.D AND C.C.. PLEASE GRANT US EXTENSION TO COMP
30 Nov 202131 Dec 2023PROJECT CIVIL WORK IS COMPLETED UPTO 14TH FLOOR BUT BALANCE WORK UP TO 20TH FLOOR REQUIRED EXTRA TIME. DUE TO CORONA EFFECT LABOUR PROBLEM AS WELL AS PASSING OFFICES ARE NOT WOR
31 Dec 202331 Dec 2026DELAY IN OBTAINING NECESSARY PERMISSION FROM DIFFERENT DEPARTMENTS. THE REASON FOR DELAY IS POLICY MATTER.

Location, Land & Connectivity

Located at DAHISAR, -, Borivali, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by CTS No 812 813, to the south by CTS No 826, to the east by L T Road and to the west by CTS No 814. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport18 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Arjun Anant Waghmare is the promoter on 3 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Arjun Anant Waghmare

Arjun Anant Waghmare
Past its declared completion dateMumbai Suburban

Other RERA-registered projects in Dahisar East

Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li
Jeandveekedarnath
possession by Dec 2026 · JE AND VEE Infrastructure
Shri Upendra Chsl
possession by Dec 2026 · Harshal Enterprises
Swayam Niketan
possession by Dec 2026 · Jainam Associates
A And O Eminente
Not filing quarterly progress reports · possession by Dec 2026 · Ashapura Housing Private Limited

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Om Shivalaya CHS Ltd
possession by Dec 2026 · Dipti Home Makers Pvt Ltd
OM Shreenath Krupa CHS LTD
possession by Dec 2026 · OM Shreenath Krupa CO Operative Housing
Om Shreepal
possession by Dec 2026 · Oscar Infrastructure Private Limited
Om Shri Ganesh CHS LTD
possession by Dec 2026 · Vardhman 9 Square LLP
OM Shri Jagannath Chsl
possession by Dec 2026 · Samarpan Homes & Developers
Om Shri Sai Darshan SRA CHS LTD
declared completion Dec 2021 · Sameer Constructions

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026