MahaRERA Property Intelligence · Raigarh

Om Unnati

P52000050075 · Taloje Majkur · promoter Om Group

Certificate SignedDue 30 Nov 2026

Delivery & Registration

MahaRERA registrationP52000050075
Registered on13 Mar 2023
Promoter-declared completion30 Nov 2026
Current statusCertificate Signed
Against today4 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Building 11G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Taloje Majkur, Survey No- 134/1/B/1, Thane, Thane, 410208. Per the filed land record, the plot is bounded to the north by Survey No- 134 1A, to the south by Survey No- 134 1 B 3, to the east by 18 M W Road and to the west by Taloja Pachnand Boundry. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park21 km
Bandra Kurla Complex (BKC)24 km
Chhatrapati Shivaji Int'l Airport25 km
Andheri MIDC / SEEPZ25 km
Lower Parel / Worli business district30 km
Nariman Point / Fort34 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Om Group is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Om Group

Other RERA-registered projects in Taloja

Ayan Skyway
possession by Sep 2026 · Ibrahim Nazirsha Mukadam
K K Residency
Not filing quarterly progress reports · possession by Sep 2026 · Shree SAI Home Makers
Majestic Planet
possession by Sep 2026 · 365days Construction LLP
Royal Yusra Heights
possession by Sep 2026 · AL-Yusra Developers LLP
3anaika
possession by Dec 2026 · Arihant Enterprises
Arihant Amisha Phase II
possession by Dec 2026 · Arihant Aashiyana Private Limited

Major developers building in Taloja

Other RERA-registered projects in Raigarh

Om Vaastu Residency
possession by Dec 2027 · OM Vaastu Realtors LLP
OM Vakratund Residency
declared completion Sep 2025 · Mandar Enterprises
Om Vista
possession by Dec 2027 · Not Available
Omega Plaza
possession by Dec 2027 · Noorul Azad Mohd Anwar Khan
Omkar
declared completion Mar 2022 · Shree Ganesh Enterprises
Omkar Aangan
possession by Jun 2029 · Maruti Ganpat Thorave

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026