PALM GARDENS

MANIVALI · ECO REALTIES PVT LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700021662

Delivery and registration

When is the project declared for completion?

PALM GARDENS is registered with MahaRERA as P51700021662 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700021662
Registered on19 Jul 2019
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PALM GARDENS record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Eco Realties is the promoter of record on 131 projects registered with MahaRERA, 12 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

131projects

registered with MahaRERA

12flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In PALM GARDENS, 28 of 52 plots filed with MahaRERA are recorded as sold or booked, about 54%, and 24 remain available.

54%sold

28 of 52 plots

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PALM GARDENS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at MANIVALI, MURBAD MANIVALI ROAD, Thane, Thane, 421401. Per the filed land record, the plot is bounded to the north by S NO 131, to the south by S NO 144, to the east by S NO 140 and to the west by S NO134. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~55 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park55 km
Andheri MIDC / SEEPZ58 km
Chhatrapati Shivaji Int'l Airport59 km
Bandra Kurla Complex (BKC)60 km
Lower Parel / Worli business district66 km
Nariman Point / Fort70 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Murbad

Shree Siddhivinayak Park C1,c2,c3
Not filing quarterly progress reports · possession by Dec 2026 · Satyashiv Developers
Arjun Heights
Not filing quarterly progress reports · possession by Dec 2026 · Nanda Arjun Shelke
Madhusudan Retreat Terraces
possession by Dec 2026 · Madhusudan Leisure Homes
SAI Krishna Heights
possession by Dec 2026 · OM SAI Developers
Swami Narendra Residency
possession by Dec 2026 · RAJ Ratneshwari Developers
Techcons Basera
possession by Dec 2026 · Techcons Constructional Engineering Co

Other RERA-registered projects in Thane

Palm Riveria
possession by Dec 2033 · YES Realty
Palm View AND Swanand CHS
possession by Dec 2026 · V J Consultants
Panchratna Sapphire
possession by Mar 2027 · Pancharatna Developers
Panchratna Sapphire
possession by Dec 2028 · Panchratna Developers
Panchsheel Midori
possession by Dec 2028 · Ananta Realty
Panchvati Complex
possession by Dec 2027 · National Associates

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.