Parkwoods Building A1

P51700009055 · promoter Aniline Construction Company

Certificate SignedDue 31 Mar 2018

Delivery & Registration

MahaRERA registrationP51700009055
Registered on19 Aug 2017
Promoter-declared completion31 Mar 2018
Current statusCertificate Signed
Against todayabout 100 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Aniline Construction Company is the promoter of record on 7 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+30.

BuildingWingsFloorsDeclared completion
A11G+3031 Mar 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
The High Court Of Judicature At BombayPIL No 36 of 20162016Pending

Location, Land & Connectivity

Located at Borivali, Mumbai Suburban, 400615. Per the filed land record, the plot is bounded to the north by Bharat Cold Storage, to the south by Cosmos Jewels, to the east by Godhbunder Road and to the west by Municipal Nallah. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~17 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park17 km
Andheri MIDC / SEEPZ18 km
Chhatrapati Shivaji Int'l Airport22 km
Bandra Kurla Complex (BKC)24 km
Lower Parel / Worli business district32 km
Nariman Point / Fort40 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aniline Construction Company Private Limited is the promoter on 3 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Aniline Construction Company Private Limited

Aniline Construction Company Private Limited
FlaggedThane
Aniline Construction Company Private Limited
FlaggedThane

Other RERA-registered projects in Owale

ACE Aristo
possession by Oct 2026 · Gaurav Land Corporation
Metro Hive D-1
possession by Dec 2026 · Vihang Infrastructure PVT LTD
Puranik Home Town - E
possession by Dec 2026 · Puranik Builders Limited
Vihang Plaza - A Commecial
possession by Dec 2026 · Vihang Enterprises
Vihang Woods
possession by Dec 2026 · Vihang Enterprises
Ace Enclave
possession by Dec 2026 · Ace Signature Homes LLP

Major developers building in Owale

Other RERA-registered projects in Thane

Parkwoods D5
possession by Dec 2026 · Aniline Construction Company Private Lim
Parkwoods D6
possession by Dec 2028 · Aniline Construction Company Private Lim
Parshava Park Phase 1
declared completion Dec 2025 · Vardhaman Enterprises
Parshava Park Phase 2
possession by Dec 2031 · Vardhaman Enterprises
Parshuram Ambaram
declared completion Apr 2026 · Veritas Red
Parshuram Heights
possession by Dec 2027 · Shree Chintamani Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.