MahaRERA Property Intelligence · Thane

PATELS RESIDENCY

P51700000865 · AMBARNATH · promoter Param Builders And

Certificate SignedDue 31 Mar 2019

Delivery & Registration

MahaRERA registrationP51700000865
Registered on23 Jul 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 88 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Param Builders And is the promoter of record on 38 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
C WING1G+731 Mar 2018
D WING1G+431 Mar 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Mar 201931 Mar 20191. We have undertaken the development of the Project and had in the application for registration filed with you under the provisions of the RERA specified the date of the completio

Location, Land & Connectivity

Located at AMBARNATH, AMBARNATH, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by 12 METER WIDE DP ROAD, to the south by SURVEY NO 3, to the east by SURVEY NO 5 and to the west by SURVEY NO 2. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park31 km
Andheri MIDC / SEEPZ34 km
Chhatrapati Shivaji Int'l Airport36 km
Bandra Kurla Complex (BKC)37 km
Lower Parel / Worli business district44 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Param Builders AND Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Param Builders AND Developers

Param Builders AND Developers
FlaggedThane

Other RERA-registered projects in Ambernath

24 High Bizbay
possession by Jul 2026 · Apex Infra
Shree Gajanan Enterprises Rukhmini CHS
possession by Jul 2026 · Shree Gajanan Enterprises Rukhmini CHS
Walekar Homes
possession by Aug 2026 · Walekar & Son's Developers
Patels Eirene
possession by Aug 2026 · Pramukh Developers
Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters

Major developers building in Ambernath

Other RERA-registered projects in Thane

Patels Residency - E Wing
declared completion Dec 2023 · Param Builders AND Developers
Patels Sapphire
declared completion Aug 2024 · Pramukh Developers
Patels Signature
declared completion Mar 2022 · Serene Infratech CO
Patels Signature Type B
declared completion Mar 2023 · Serene Infratech CO
Patels Venus
possession by Jun 2028 · Bechar Raghavji Patel
Patels Vrindavan
declared completion Jun 2025 · Desire Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026