MahaRERA Property Intelligence · Mumbai City

Pearl Aurelia

P51900003787 · Dadar (East) · promoter Rishiraj Builders Llp

Certificate SignedDue 30 Mar 2022

Delivery & Registration

MahaRERA registrationP51900003787
Registered on06 Aug 2017
Promoter-declared completion30 Mar 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rishiraj Builders Llp is the promoter of record on 4 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Pearl Aurelia1G+14-

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000021006017/02/2022Kaustubha Phene vs Rishiraj Builders LLPorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202230 Sep 2021• The construction of structure upto 11 floors out of total proposed 12 floors is completed, • The brickwork for walls, plumbing work, electrical wiring work, water proofing work

Location, Land & Connectivity

Located at Dadar (East), Dinshaw Master Road, Mumbai City, Mumbai City, 400014. Per the filed land record, the plot is bounded to the north by Dinshaw Master Road, to the south by 700A, to the east by Plot No 699 and to the west by Road No 4. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dadar East

Anchor Sky D
Deregistered by MahaRERA · possession by Dec 2026 · Om Shanti Housing Development Company
Yash Supriya
possession by Dec 2026 · Yash Construction Company
Bhalchandra Niwas CHS
possession by Dec 2026 · Ishaan Realtors
Nine Reflex
possession by Dec 2026 · Reflex Projects LLP
Chirag Heights
possession by Dec 2026 · Nettheim Builders LLP
EL Mejor
possession by Dec 2026 · Arth Realtech Spaces PVT LTD

Other RERA-registered projects in Mumbai City

Pearl Bay View
possession by Dec 2026 · Pearl Concept Constructions
Pearl Crest
declared completion Dec 2021 · Rishiraj Developers Private Limited
Pearl Elegance
possession by Dec 2028 · Pearl Concept Realty LLP
Pearl Harmony
declared completion Mar 2022 · Pearl Concept Constructions
Pearl Heights
possession by Jun 2027 · M/s Sitesh Developers
Pearl Residency
declared completion Apr 2023 · Pushpa Construction CO

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026