Mumbai/Project record

MahaRERA · the public record

PEARL HERITAGE

Vile Parle East · HARI OM CONSTRUCTION

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

22units filed as unsoldInventory · 13 September 2026
30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800010436

Delivery and registration

When is the project declared for completion?

PEARL HERITAGE is registered with MahaRERA as P51800010436 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800010436
Registered on24 Aug 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PEARL HERITAGE record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

What the filings record, home by home

Read from MahaRERA on 13 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 9 homes carry one, and 22 of the 35 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
B-102838 sqftRs 2.4831 cr typical, over Rs 2.2047 cr to Rs 2.9689 cr4 filed on this stack, floors 4–7

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In PEARL HERITAGE, 8 of the 22 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 21 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
PEARL HERITAGE - WING B1G+830 Dec 2022
PEARL HERITAGE - WING C1G+830 Dec 2022

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for PEARL HERITAGE, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000019434623/10/2020RAMESH SANJEEVA SHETTY vs HARI OM CONSTRUCTIONorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2023We had registered our project on 24.08.2017 on MahaRERA portal. However our project entry path was blocked by a property owner who had executed a development agreement dated 30th D
30 Dec 202330 Dec 2024We had registered our project on 24.08.2017 on MahaRERA portal. However our project entry path was blocked by a property owner who had executed a development agreement dated 30th D

Location, Land & Connectivity

Located at Vile Parle East, Andheri, Mumbai Suburban, 400057. Per the filed land record, the plot is bounded to the north by CTS NO 200, to the south by INTERNAL ROAD AND CTS NO 198, to the east by KOLDONGARI ROAD and to the west by CTS NO 195 AND 259. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Bandra Kurla Complex (BKC)7 km
Lower Parel / Worli business district14 km
Nariman Point / Fort22 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Hari OM Construction is the promoter on 6 MahaRERA-registered projects, of which 3 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Hari OM Construction

Hari OM Construction
Not filing quarterly progress reportsMumbai Suburban
Hari OM Construction
Not filing quarterly progress reportsMumbai Suburban
Hari OM Construction
FlaggedThane

Other RERA-registered projects in Vile Parle East

Moti Madhav
possession by Sep 2026 · Aadhya Skyvista
Neumec Niwara
possession by Sep 2026 · Neumec Venture
Yeshwant Sadan
possession by Sep 2026 · ARG Life Spaces LLP
Vile Parle Mamata Chsl
possession by Oct 2026 · Dhruv Infrastructure
Vanmala Nivas CHS LTD
possession by Nov 2026 · AMI Infra Realtors
ZEE Nayak
possession by Dec 2026 · Pragatee ZEE

Other RERA-registered projects in Mumbai Suburban

Pearl Icon
possession by Dec 2030 · Bahist Enterprises PVT LTD
Pearl Orchid
possession by Dec 2026 · Chandiwala Enterprises Private Limited
Pearl Palace
declared completion Dec 2021 · Chandiwala Enterprises
Pearl Platinum A Wing
possession by Dec 2028 · Chandiwala Enterprises
Pearl Platinum Wing B
possession by Dec 2028 · Chandiwala Enterprises
Pearl Providence
possession by Dec 2029 · Chandiwala Enterprises Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026