Mumbai/Project record

MahaRERA · the public record

PINK CITY TRIDENT PHASE 2

AMBERNATH EAST DISTRICT THANE · AMI INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Apr 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Apr 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700001716

Delivery and registration

When is the project declared for completion?

PINK CITY TRIDENT PHASE 2 is registered with MahaRERA as P51700001716 and the promoter has declared completion for 30 Apr 2022.

30 Apr 2022

declared completion

53months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700001716
Registered on29 Jul 2017
Promoter-declared completion30 Apr 2022
Current statusCertificate Signed
Against todayabout 53 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PINK CITY TRIDENT PHASE 2 record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PINK CITY TRIDENT PHASE 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
WING A1G+830 Apr 2020
WING B1G+1330 Apr 2020
WING C1G+830 Apr 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2021The project is under construction & we have completed more than 95% work on the project. However due to imposition of lockdown and consequently migration of labour and contractors
31 Mar 202131 Oct 2021We, Ami Infra, have registered for our real estate project "Ami Infra Trident Phase 2" bearing registration no. P51700001716.The date of completion of the project was given as 31.0

Location, Land & Connectivity

Located at AMBERNATH EAST DISTRICT THANE, P 9353 GUT NO 48 PINK CITY NEAR ROYAL PARK NAVARE NAGAR , Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by CTS NO 9278, to the south by 12 METER DP ROAD, to the east by GUT NO 45 CTS NO 9352 and to the west by 18 METER DP ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~31 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park31 km
Andheri MIDC / SEEPZ34 km
Chhatrapati Shivaji Int'l Airport36 km
Bandra Kurla Complex (BKC)37 km
Lower Parel / Worli business district44 km
Nariman Point / Fort49 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Pinnacle Structures
possession by Mar 2030 · Not Available
Pinnacle Vatika
possession by Dec 2029 · MM Pinnacle Buildcon LLP
Pinnacle West
possession by Jun 2031 · Gayatri Infra
Pioneer Park 2
declared completion Mar 2022 · Shubham Enterprises
Pioneer - THE View
possession by Dec 2029 · Pioneer Infra
Pitambare Tower
possession by Mar 2028 · Aditi Builders AND Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026