Mumbai/Project record

MahaRERA · the public record

PRABHAKAR APARTMENT

BHAYANDER WEST · SHRI SAMARTHA DEVELOPER

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700020652

Delivery and registration

When is the project declared for completion?

PRABHAKAR APARTMENT is registered with MahaRERA as P51700020652 and the promoter has declared completion for 30 Jun 2019.

30 Jun 2019

declared completion

87months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700020652
Registered on30 Apr 2019
Promoter-declared completion30 Jun 2019
Current statusCertificate Signed
Against todayabout 87 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for PRABHAKAR APARTMENT record 1 quarterly progress report since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 1 quarterly progress report on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Shri Samartha Developer is the promoter of record on 25 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

25projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for PRABHAKAR APARTMENT in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
PRABHAKAR APARTMENT1G+430 Jun 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at BHAYANDER WEST, BAKERY GALLI, Thane, Thane, 401101. Per the filed land record, the plot is bounded to the north by 832, to the south by 828, to the east by 834 and to the west by 891. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander West

Saroj Chandra Krupa
possession by Oct 2026 · S C Associates
Chandanbala
possession by Dec 2026 · Hemant Sagarmal Jain
Dagdu Bua Heights
possession by Dec 2026 · Siddhivinayak Realty
Magic OM Heights
possession by Dec 2026 · Magic Shanti Developer
N G Silver Spring Phase III
possession by Dec 2026 · RNA Builders
Prabha Leela
Not filing quarterly progress reports · possession by Dec 2026 · Rudraksha Realty

Other RERA-registered projects in Thane

Prabhu Darshan CO-Operative Housing Society Limited
possession by Dec 2026 · NYP Developers
Pradeep CO-Operative Housing Society LTD
possession by Sep 2027 · Squarefeet Real Estate
Pradhan Mantri Awas Yojana - Urban
possession by Dec 2027 · Kulgaon Badlapur Municipal Council
Pragati Om Gulmohar
possession by Sep 2027 · Pragati Homes
Prakash Landmark
possession by Aug 2030 · RAI Lifespaces
Prakash Palace
possession by Dec 2026 · R K Builders And Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026