PRIYANSHI RESIDENCY

P52000016200 · PANVEL · promoter Shivkrupa Builders And

Certificate SignedDue 31 Dec 2025

Delivery & Registration

MahaRERA registrationP52000016200
Registered on23 Apr 2018
Promoter-declared completion31 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shivkrupa Builders And is the promoter of record on 19 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
PRIYANSHI RESIDENCY BLDG 11G+431 Dec 2020
PRIYANSHI RESIDENCY BLDG 21G+431 Dec 2020
PRIYANSHI RESIDENCY BLDG 31G+331 Dec 2020
PRIYANSHI RESIDENCY BLDG 41G+331 Dec 2020

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000040822729/01/2024Dhanraj Raman Mhatre vs 1.M/s. Shivkrupa Builders & Developers, The partnership Firmorder passed
CC1260285115/05/2026UDAY DATTARAM CHANDURKAR vs SHIVKRUPA BUILDERS AND DEVELOPERSpending / no order on file

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Jun 202130 Sep 2022DUE TO SOME PERSONAL ISSUES AND SHORATGE OF FUNDS PROJECT IS YET NOT COMPLETED
30 Jun 202131 Dec 2021THE PROJECT IS DELAYED TO PANADAMIC OF COVID 19 AS LOCKDOWN WAS THERE WORK WAS NOT IN PROGRESS AS REQUIRED SO PLEASE EXTEND THE PROJECT DATE
30 Jun 202131 Dec 2025The delay in project completion is primarily attributable to a combination of unforeseen and unavoidable circumstances. Firstly, an internal dispute with a former partner significa

Location, Land & Connectivity

Located at PANVEL, PANVEL, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by PROPERTY OF GOWARI, to the south by VILLAGE ROAD, to the east by PROPERTY OF SAPRE and to the west by VILLAGE ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park27 km
Bandra Kurla Complex (BKC)27 km
Chhatrapati Shivaji Int'l Airport29 km
Lower Parel / Worli business district30 km
Andheri MIDC / SEEPZ30 km
Nariman Point / Fort32 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Ambaji Residency
possession by Jul 2026 · Vishal Tukaram Patil
Bayview
possession by Jul 2026 · Skyline Realbuild LLP
Delta Heights
possession by Jul 2026 · Shreenathji Organisers Pvt. Ltd.
Micron Residency
possession by Jul 2026 · Micron Infra
Shree Mahadev Residency
possession by Jul 2026 · SK Developers
Aishwarya Cooperative Housing Society
possession by Aug 2026 · Royal Enterprises

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Progressive Grande
declared completion Dec 2022 · Progressive Homes
Progressive Prive
declared completion Dec 2025 · Progressive Homes
Punir Gaurav - B Wing
declared completion Apr 2026 · Punir Gaurav Developers Pvt Ltd.
Punir Gaurav PH 1- Shriwardhan
declared completion Sep 2020 · Punir Gaurav Developers Pvt Ltd.
Punir Gaurav - Shriwardhan
declared completion Apr 2019 · Punir Gaurav Developers Pvt Ltd.
Punit Imperia
possession by Jul 2027 · Punit Realty

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.