Mumbai/Project record

MahaRERA · the public record

RADHA HOME

KARANJADE · SHREE MAULI KRUPA DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

01 Feb 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

01 Feb 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000030120

Delivery and registration

When is the project declared for completion?

RADHA HOME is registered with MahaRERA as P52000030120 and the promoter has declared completion for 01 Feb 2022.

01 Feb 2022

declared completion

55months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000030120
Registered on31 Jul 2021
Promoter-declared completion01 Feb 2022
Current statusCertificate Signed
Against todayabout 55 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RADHA HOME record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 3 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RADHA HOME in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
RADHA HOME1G+501 Feb 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at KARANJADE, SECTOR R3, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by 9 MM WIDE ROAD, to the south by PLOT SECTOR R3, to the east by PLOT SECTOR R3 and to the west by 15 MM WIDE ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Radha Krishna Complex
declared completion Dec 2023 · Dimension Builders & Developers
Radha Niwas
declared completion Mar 2023 · Ideal Builder
Radhekrishna Apartment
declared completion Sep 2024 · RK Builders AND Developers
Radiant Corner
possession by Dec 2026 · Radiant Infra
Raghunath
possession by Dec 2026 · Aayushi Corporation
Raghunath Niwas
declared completion Dec 2023 · Raghunath Joma Mokal

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026