MahaRERA Property Intelligence · Mumbai Suburban

Radhakrishnan Redevelopment project

P51800007300 · promoter Vibrant Properties

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51800007300
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Vibrant Properties is the promoter of record on 6 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Radha Krishna1G+819 Dec 2020

Complaints & Orders

2 complaints are on the MahaRERA record for this project, with orders passed in 2. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019844624/09/2021Mahendra Himatlal Gandhi vs M/s Vibrant Propertiesorder passed
CC00600000019844824/09/2021Mrs. Sonal Kirit Zaveri vs M/s Vibrant Propertiesorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. 1 is still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Bombay City Civil Court At BombaySc suit no 26582016Pending

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202431 Dec 2024Due to litigations between Society members and developers, the Project was stalled for a few years. Now Since everything is resolved amicably we assure you to complete the project
31 Dec 202419 Dec 2020DELAY OF REASON Subject: - Request letter for extension for (1) one year under MahaRERA Act 2016 dur to the below-mentioned reasons of delay caused in construction activity.

Location, Land & Connectivity

Located at Kurla, Mumbai Suburban, 400077. Per the filed land record, the plot is bounded to the north by By the property bearing no 111, to the south by Dr Ambedker D P Road, to the east by Residential building Smita CHSL and to the west by Residential building Satyadeep CHSL. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Baldevsingh Thakur SRA Coop HSG SOC LTD
possession by Jul 2026 · Krishna Narsingrao Pimple
Palatina
possession by Jul 2026 · Tanishq Builders
Vihar Heights
possession by Aug 2026 · Saptrishi Homes LLP
Poonam Celeste
possession by Aug 2026 · PL7 Realty Pvt. Ltd.
Hema Apartments CO-Operative Housing Society Limited
possession by Sep 2026 · Hema Appartments CO-Operative Housing So
Centrona ZEN-A
possession by Dec 2026 · Elevated Avenue Realty LLP

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai Suburban

Radhakunj CHS
declared completion Jan 2019 · AUM Developers
Radhakunj CHS LTD
declared completion Nov 2020 · Siddhi Builders & Developers
Radiant 59
possession by Dec 2026 · Veer Jalaram Developers
Radius Residency And Anand Bhuvan
declared completion Dec 2023 · Radius Project Developers LLP
Rafiq Residency
declared completion Jun 2025 · Al Ammar Developers
Raghav Amara
declared completion Sep 2024 · Raghav RAJ Builders & Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026