Mumbai/Project record

MahaRERA · the public record

RADHAKUNJ CHS LTD

ghatkopar · SIDDHI BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Nov 2020declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Nov 2020

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005729

Delivery and registration

When is the project declared for completion?

RADHAKUNJ CHS LTD is registered with MahaRERA as P51800005729 and the promoter has declared completion for 30 Nov 2020.

30 Nov 2020

declared completion

70months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005729
Registered on11 Aug 2017
Promoter-declared completion30 Nov 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RADHAKUNJ CHS LTD record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RADHAKUNJ CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
RADHAKUNJ CHS LTD1G+15-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for RADHAKUNJ CHS LTD, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000002285411/01/2018RADHAKUNJ CHS LTD. (society) vs Siddhi Builders and Developersorder passed

A co-operative housing society is recorded as the complainant (RADHAKUNJ CHS LTD.), and MahaRERA has passed an order.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 May 2020An Arbitration suite was pending and an consent terms was filed with society extending the period of completion to 31 May 2020. The Construction of the building is 95% Complete an
31 May 202031 May 2020Arbitration and legal matters between society and developer.

Location, Land & Connectivity

Located at ghatkopar, pestom sagar road no 3, Borivali, Mumbai Suburban, 400089. Per the filed land record, the plot is bounded to the north by CTS NO 634, to the south by 18 METER ROAD, to the east by OPEN SPACE RG and to the west by CTS NO 633 AND 632 . These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Bandra Kurla Complex (BKC)3 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park6 km
Andheri MIDC / SEEPZ8 km
Lower Parel / Worli business district11 km
Nariman Point / Fort18 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Orient Regency Building No. 1
possession by Dec 2026 · Orient Combine
Sree Sudarshan Heights
possession by Dec 2026 · AUM SAI Constructions Private Limited
Srushtiraj Tower
possession by Dec 2026 · Chinnaiah Venkatesh Gowda
Promesa Midtown
possession by Dec 2026 · Darshan Properties
Vishwasangam
possession by Dec 2026 · Vishwashakti Cooperative Housing Society
Ampple-ONE
possession by Mar 2027 · Amppletech Projects Private Limited

Other RERA-registered projects in Mumbai Suburban

Radiance Regalia
possession by Dec 2028 · Radiance Builders AND Developers LLP
Radiant 59
possession by Dec 2026 · Veer Jalaram Developers
Radius Residency And Anand Bhuvan
declared completion Dec 2023 · Radius Project Developers LLP
Rafiq Residency
declared completion Jun 2025 · Al Ammar Developers
Raghav Ananta
possession by Dec 2027 · Raghav RAJ Builders & Developers LLP
Raghav Avenue
possession by Jun 2029 · Raghav RAJ Builders & Developers LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026