30 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700017230

Delivery and registration

When is the project declared for completion?

Rai s AARAGYA is registered with MahaRERA as P51700017230 and the promoter has declared completion for 30 Dec 2026.

30 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700017230
Registered on24 Jul 2018
Promoter-declared completion30 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Rai s AARAGYA record 32 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Rai Residency is the promoter of record on 149 projects registered with MahaRERA, 17 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

149projects

registered with MahaRERA

17flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Rai s AARAGYA in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+23.

BuildingWingsFloorsDeclared completion
Rai s AARAGHYA BLDG 02 B WING1G+531 Dec 2025
RAI s AARAGHYA BLDG 01 A WING1G+831 Dec 2025
RAIS AARAGHYA BLDG NO 3 C WING1G+1230 Jun 2026
RAIS AARAGHYA BLDG NO 4 D WING1G+630 Jun 2026
RAIS AARAGHYA BLDG NO 5 E WING1G+2330 Jun 2026
RAIS AARAGHYA PROPOSED1-30 Jun 2026

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for Rai s AARAGYA, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000040839707/12/2023Lata Balaram Gaikwad vs Rai Residency P Ltd through its Director Mr Manoj Ramsakal Raiorder passed

Location, Land & Connectivity

Located at Tisgoan, Tisgoan road S no46, Kalyan, Thane, 421306. Per the filed land record, the plot is bounded to the north by Hissa No 7 , to the south by Hissa No 3, to the east by Hissa No 2 and to the west by Hissa No 6. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

RAI Residency Private Limited is the promoter on 17 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every RAI Residency Private Limited project & its RERA track record →

Other flagged projects by RAI Residency Private Limited

RAI Residency Private Limited
FlaggedThane
RAI Residency Private Limited
FlaggedThane
RAI Residency Private Limited
FlaggedThane
RAI Residency Private Limited
Past its declared completion dateThane
RAI Residency Private Limited
FlaggedThane
RAI Residency Private Limited
Not filing quarterly progress reportsThane

Other RERA-registered projects in Kalyan East

Kohinoor Eden
possession by Sep 2026 · KGI Realty Private Limited
Kohinoor Eden Ph 2
possession by Sep 2026 · KGI Realty Private Limited
Krishna Glory
possession by Oct 2026 · Tulsi Kimaya Construction
Trimurti Garden
possession by Dec 2026 · SAI Narayan Developers
Rai S Heaven
possession by Dec 2026 · RAI Residency Private Limited
Ashwathi Heights
possession by Dec 2026 · Prachiti Constructions

Major developers building in Kalyan East

Other RERA-registered projects in Thane

RAI S Galaxy
possession by Dec 2029 · RAI Residency Private Limited
Rai S Heaven
possession by Dec 2026 · RAI Residency Private Limited
RAI S Nisarg
declared completion Dec 2025 · RAI Residency Private Limited
Raigad By Bhagwati Haware – Wing - A
possession by Dec 2034 · Bhagwati Haware Properties Supertech
Raigad CO-OP. Hsg. Soc. LTD
possession by Aug 2027 · Utkarsha Construction
RAJ Cornerstone
possession by Dec 2029 · Raj Superstructure

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026