Mumbai/Project record

MahaRERA · the public record

RAJ SHREE VAASTU

HARIGRAM · R PUROHIT SPACE DEVELOPERS PVT. LTD

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000008944

Delivery and registration

When is the project declared for completion?

RAJ SHREE VAASTU is registered with MahaRERA as P52000008944 and the promoter has declared completion for 30 Jun 2022.

30 Jun 2022

declared completion

51months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000008944
Registered on19 Aug 2017
Promoter-declared completion30 Jun 2022
Current statusCertificate Signed
Against todayabout 51 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAJ SHREE VAASTU record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Purohit Space Developers is the promoter of record on 10 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

10projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAJ SHREE VAASTU in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING-1/ A WING1G+4-
BUILDING-2/B WING1G+4-
BUILDING-1/C WING1G+4-
BUILDING-1/D WING1G+3-
BUILDING-2/E WING1G+4-
BUILDING-2/F WING1G+4-
BUILDING-2/G WING1G+4-

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for RAJ SHREE VAASTU, with orders passed in 1 of them.

1complaint

1with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000029243723/08/2022Bhushan Hanmant Mahadik vs Rita Purohit & Amrit Purohitorder passed

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Dec 2021Statutory permissions/clearances from various authorities are pending. We seek to apply for these permissions with various statutory departments and hence, we request you to kindly

Location, Land & Connectivity

Located at HARIGRAM, SURVEY NO 1/8 AND SURVEY NO 1/9, Panvel, Raigarh, 410206. Per the filed land record, the plot is bounded to the north by AROUND 5 MTRS ROAD, to the south by PLOT NO 1-10, to the east by PLOT NO 1-7 and to the west by PLOT NO 1-11. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~28 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park28 km
Bandra Kurla Complex (BKC)30 km
Chhatrapati Shivaji Int'l Airport31 km
Andheri MIDC / SEEPZ32 km
Lower Parel / Worli business district34 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

RAJ Someshwar
declared completion Dec 2019 · Rituraj Infra Project Private Limited
Rajesh Presidency
declared completion Apr 2018 · SAI Shri Home Makers
Rajhans Evana Phase 1
possession by Dec 2029 · Joydale Infracon LLP
Rajkumari Apartment
possession by Dec 2028 · Shiv Construction Company
Rajshri Park Phase 1
declared completion Sep 2022 · Rajshri Builder
Raksha Avenue
possession by Dec 2028 · Mohamed Hussain Habib Pathan

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026