Mumbai/Project record

MahaRERA · the public record

Rajendra Jhaveri Residence

Goregaon West · Usha Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2018declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2018

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800005957

Delivery and registration

When is the project declared for completion?

Rajendra Jhaveri Residence is registered with MahaRERA as P51800005957 and the promoter has declared completion for 31 Dec 2018.

31 Dec 2018

declared completion

93months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800005957
Registered on14 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 93 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Rajendra Jhaveri Residence record 6 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 6 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Usha Developers is the promoter of record on 167 projects registered with MahaRERA, 25 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

167projects

registered with MahaRERA

25flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Rajendra Jhaveri Residence in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+15.

BuildingWingsFloorsDeclared completion
Rajendra Jhaveri Residence1G+15-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at Goregaon West, Borivali, Mumbai Suburban, 400104. Per the filed land record, the plot is bounded to the north by CTS 630, to the south by Jhawahar Rd 2, to the east by CTS 628 and to the west by CTS no 632. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ5 km
Powai / Hiranandani business park9 km
Chhatrapati Shivaji Int'l Airport9 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district18 km
Nariman Point / Fort26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Goregaon West

Hitendra Dhamm Shabha Co-Operative Housing Society Limited
possession by Sep 2026 · Crystal Construction Company
Sahakar Revanta
possession by Sep 2026 · Sahakar Builders & Developers
Vallabh Krupa Chsl
possession by Oct 2026 · Gun Rajan Constructions
Siddharth Nagar Gulmohar CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Paschim Jagruti CHS LTD
possession by Dec 2026 · Shivam Parivar Developers PVT LTD
Siddharth Nagar Swami Vivekanand Chsl
possession by Dec 2026 · Dhariwal Developers Private Limited

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Rajendra Nagar Omsai CO-Operative Housing Society Limited
possession by Dec 2027 · Sunil Harishchandra Keni
Rajendra Nagar RAJ Kiran Co.op. Hsg. Soc. LTD
possession by Dec 2026 · H M Realty
Rajendra Nagar Swagat Chsl
declared completion Dec 2025 · Riddhi Constructions
Rajgopal Building
declared completion Sep 2026 · Harmony AND Prosperity Developer
Rajgriha Smriti
declared completion Mar 2025 · Padamavati Builders & Infrastructure
Rajhans Solitaire
declared completion Aug 2026 · Rajhans Residency

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026