MahaRERA Property Intelligence · Mumbai Suburban

RAJHANS SPLENDID

P51800010165 · promoter Rajhans Reality

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51800010165
Registered on24 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rajhans Reality is the promoter of record on 8 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 125 homes filed with MahaRERA, 87 are sold/booked and 38 remain available (~70% sold) — selling steadily. Buyers have committed ₹85.20 Cr in agreement value so far. Of that, ₹76.72 Cr (~90%) is already collected, ₹8.48 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 87 registered agreements, the effective carpet rate is ₹19,258/sqft (typical range ₹15,501–₹25,624) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1101442 sqft (41.06 sqm)₹61.77 Lakh
Floor 1104450 sqft (41.81 sqm)₹62.89 Lakh
Floor 1105442 sqft (41.06 sqm)₹61.77 Lakh
Floor 161601442 sqft (41.06 sqm)₹73.91 Lakh
Floor 161602820 sqft (76.18 sqm)₹1.37 Cr
Floor 161603634 sqft (58.9 sqm)₹1.06 Cr
Floor 161604450 sqft (41.81 sqm)₹75.26 Lakh
Floor 161605442 sqft (41.06 sqm)₹73.91 Lakh
Floor 171701442 sqft (41.06 sqm)₹73.91 Lakh
Floor 171702820 sqft (76.18 sqm)₹1.37 Cr
Floor 171703634 sqft (58.9 sqm)₹1.06 Cr
Floor 171704450 sqft (41.81 sqm)₹75.26 Lakh
Floor 171705442 sqft (41.06 sqm)₹73.91 Lakh
Floor 181801442 sqft (41.06 sqm)₹73.91 Lakh
Floor 181802820 sqft (76.18 sqm)₹1.37 Cr
Floor 181803634 sqft (58.9 sqm)₹1.06 Cr
Floor 181804450 sqft (41.81 sqm)₹75.26 Lakh
Floor 181805442 sqft (41.06 sqm)₹73.91 Lakh
Floor 191901442 sqft (41.06 sqm)₹73.91 Lakh
Floor 191902820 sqft (76.18 sqm)₹1.37 Cr
Floor 191903634 sqft (58.9 sqm)₹1.06 Cr
Floor 191904450 sqft (41.81 sqm)₹75.26 Lakh
Floor 191905442 sqft (41.06 sqm)₹73.91 Lakh
Ground/Floor 0SHOP-1261 sqft (24.25 sqm)₹45.60 Lakh
Ground/Floor 0SHOP-10190 sqft (17.66 sqm)₹33.21 Lakh
Ground/Floor 0SHOP-11285 sqft (26.48 sqm)₹49.79 Lakh
Ground/Floor 0SHOP-2255 sqft (23.73 sqm)₹44.62 Lakh
Ground/Floor 0SHOP-3243 sqft (22.59 sqm)₹42.48 Lakh
Ground/Floor 0SHOP-4233 sqft (21.63 sqm)₹40.67 Lakh
Ground/Floor 0SHOP-5231 sqft (21.48 sqm)₹40.39 Lakh
Ground/Floor 0SHOP-6166 sqft (15.39 sqm)₹28.94 Lakh
Ground/Floor 0SHOP-7147 sqft (13.64 sqm)₹25.65 Lakh
Ground/Floor 0SHOP-8104 sqft (9.69 sqm)₹18.22 Lakh
Ground/Floor 0SHOP-9161 sqft (14.92 sqm)₹28.05 Lakh
PodiumOFFICE-11,528 sqft (141.99 sqm)₹2.46 Cr
PodiumOFFICE-2677 sqft (62.87 sqm)₹1.09 Cr
PodiumOFFICE-3858 sqft (79.73 sqm)₹1.38 Cr
PodiumOFFICE-4296 sqft (27.49 sqm)₹47.55 Lakh

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+21 and 125 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RAJHANS SPLENDID1G+2112530 Dec 2022

Unit mix on the filing: 110 residential and 15 non-residential (shops/offices).

Complaints & Orders

5 complaints are on the MahaRERA record for this project, with orders passed in 5. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019618604/03/2021Niraj Kakad vs RAJESH VALLABHBHAI SHINGALAorder passed
CC1250281211/08/2025Shalaka Nilesh Nimkar vs RAJHANS REALITYorder passed
CC1250340423/09/2025Pramod Premchand Kannaujiya vs RAJHANS REALITYorder passed
CC1250341824/09/2025Rohin Dhatingan vs RAJHANS REALITYorder passed
CC1250343426/09/2025Narendrasingh Sisodiya vs RAJHANS REALITYorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 2 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202431 Dec 2023DUE TO HEIGHT RESTRICTIONS IN OUR WARD , WE HAVE NOT RECEIVED AVAITION NOC YET AND DUE TO THIS OUR WORK IS GOING ON AT SLOW PASE AS WE HAVE BEEN GRANTED THE IOD FOR 19TH UPPER FLOO
31 Dec 202431 Dec 2024DUE TO HEIGHT RESTRICTION OF CIVIL AVAITION IN DAHISAR EAST WE ARE NOT ABLE TO GET FURTHER CC AND WE HAVE ALREADY RECIEVED IOD FOR 19TH FLOOR BUT CC IS RESTRICTED TILL 15TH FLOOR

Location, Land & Connectivity

Located at 0, Borivali, Mumbai Suburban, 400068. Per the filed land record, the plot is bounded to the north by CTS NO 2645 A, to the south by 9 MTR WIDE EXISITING ROAD, to the east by CTS NO 2594 and to the west by 18 MTR WIDE D P ROAD. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~13 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Andheri MIDC / SEEPZ13 km
Powai / Hiranandani business park15 km
Chhatrapati Shivaji Int'l Airport17 km
Bandra Kurla Complex (BKC)20 km
Lower Parel / Worli business district28 km
Nariman Point / Fort36 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dahisar East

Sahakar Vista
possession by Jul 2026 · Sahakar Creation
Commercial Wing - NL Plaza And Residential Wing - NL Krishna
possession by Aug 2026 · Beautiful Properties Private Limited
Krishna Kripa
possession by Aug 2026 · Skyla Developers LLP
RAJ Capital
possession by Aug 2026 · RAJ Insignia Private Limited
Bhaveshwar Heights
possession by Sep 2026 · Shree Krishna Real Estate And Developers
Padma Apartment CO-Operative Housing Society Limited
possession by Sep 2026 · Haritara Construction Company Private Li

Major developers building in Dahisar East

Other RERA-registered projects in Mumbai Suburban

Rajhans Vandana
possession by Dec 2027 · Rajhans Constructions
Rajinfinia Phase II Wing A Wing B Wing C
declared completion Dec 2024 · Rajsanket Realty Limited
Rajita Villa
declared completion Feb 2024 · Siddharth Enterprises
Rajkamal
declared completion Nov 2021 · RAJ Constructions
Rajkamal
declared completion Jun 2025 · Khushi Associates
Rajlaxmi Heights Chsl
possession by May 2027 · Rajmudra Constructions Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026