12units filed as unsoldInventory · 20 September 2026
31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
16registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · PR1240002501628

Delivery and registration

When is the project declared for completion?

RAMA PRABHAKAR TOWER is registered with MahaRERA as PR1240002501628 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationPR1240002501628
Registered on28 Nov 2025
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RAMA PRABHAKAR TOWER record 3 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Ekvira Construction is the promoter of record on 11 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

11projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In RAMA PRABHAKAR TOWER, 0 of 12 homes filed with MahaRERA are recorded as sold or booked, about 0%, and 12 remain available.

0%sold

0 of 12 homes

Counts as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. The project registers 16 homes in total, while this sold/unsold inventory filing covers 12 of them.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

The units recorded as unsold on the filing. The reckoner value is the government's ready-reckoner assessment the promoter filed against that unit, the figure stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home.

FloorUnitCarpetGovt reckoner value
Floor 1101200 sqft (18.58 sqm)₹12.00 Lakh
Floor 1102460 sqft (42.73 sqm)₹27.59 Lakh
Floor 2201200 sqft (18.58 sqm)₹12.00 Lakh
Floor 3301200 sqft (18.58 sqm)₹12.00 Lakh
Floor 4401200 sqft (18.58 sqm)₹12.00 Lakh
Floor 4402460 sqft (42.73 sqm)₹27.59 Lakh
Floor 5501200 sqft (18.58 sqm)₹12.60 Lakh
Floor 5502460 sqft (42.73 sqm)₹28.97 Lakh
Floor 6601200 sqft (18.58 sqm)₹12.60 Lakh
Floor 6602460 sqft (42.73 sqm)₹28.97 Lakh
Floor 7701335 sqft (31.12 sqm)₹21.10 Lakh
Ground/Floor 01100 sqft (9.29 sqm)₹7.47 Lakh

The inventory filing also declares: 4 owner/investor-held.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RAMA PRABHAKAR TOWER in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 20 September 2026

What the filings record, home by home

Read from MahaRERA on 20 September 2026

No home in RAMA PRABHAKAR TOWER carries a registered agreement value on its MahaRERA filing, so there is no record here of what anyone has paid. What the promoter has filed is the government ready reckoner value for 16 homes — the Annual Statement of Rates valuation, with each home’s carpet area and floor already applied. Across them that is Rs 6,299 a sq ft typical, over Rs 5,999 to Rs 7,470.

A reckoner value is the basis stamp duty is charged on. It is not a price anyone paid, not an asking price, and not a valuation of the home to you.

The Reckoner Record lists all 16 of them — each home, its RERA carpet area, the valuation filed against it and the rate that works out to. It is the filing copied, not a reading of it.

See all 16 filed valuations — ₹999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 16 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RAMA PRABHAKAR TOWER1G+716-

Unit mix on the filing: 13 residential and 3 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NR WATER TANK, VARTAK WARD, Vasai, Palghar, 401303. Per the filed land record, the plot is bounded to the north by DONGARPADA LAKE, to the south by ANANT SPACE BLDG, to the east by KULSWAMINI BUNGLOW and to the west by SHIVSHALINI BLDG. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~21 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ21 km
Powai / Hiranandani business park22 km
Chhatrapati Shivaji Int'l Airport26 km
Bandra Kurla Complex (BKC)28 km
Lower Parel / Worli business district37 km
Nariman Point / Fort45 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Ekvira Construction is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Virar West

Mayfair Virar Gardens Building NO 23, 24 And 25
possession by Sep 2026 · Mayfair Housing
Dattachhaya
possession by Nov 2026 · Jagdish Manohar Mhatre
Solaris Wing E-1 Hdil Layout
possession by Dec 2026 · Sunshine Developers
Star ERA
possession by Dec 2026 · Star Builders & Developers
Sugandhi Square
possession by Dec 2026 · R. N. Realty
Vitthal Haven
possession by Dec 2026 · Sushila Builders & Developers

Other RERA-registered projects in Palghar

Ramashray
declared completion Jun 2022 · Pariksheet Ramkrishna Dandekar
Ramayan LUV B Wing
possession by Dec 2030 · Nine Realcon Builders LLP
Ramchandra Heights Building NO 2
possession by Dec 2028 · Manaki Builders
Ramchandra Residency Building No. 2
declared completion Jul 2025 · Himali Construction
Ramchandra Sankul
declared completion Aug 2019 · Sai Rath Construction Co.
Ramesh Heights
possession by Dec 2026 · S S Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.