Ramchandra Residency Building No. 2

chandansar · Himali Construction

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2025declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000024898

Delivery and registration

When is the project declared for completion?

Ramchandra Residency Building No. 2 is registered with MahaRERA as P99000024898 and the promoter has declared completion for 31 Jul 2025.

31 Jul 2025

declared completion

14months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000024898
Registered on09 Mar 2020
Promoter-declared completion31 Jul 2025
Current statusCertificate Signed
Against todayabout 14 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Ramchandra Residency Building No. 2 record 23 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Himali Construction is the promoter of record on 2 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Ramchandra Residency Building No. 2 in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Ramchandra Residency Bldg no 21G+8-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered31 Jul 2024We M/s. Himali Construction are constructing a building known as “Ramchandra Residency, Building No. 2”, Situated at Survey No. 143, H. No. 3, Village Kopri, Taluka Vasai, District
31 Jul 202431 Jul 2025Reasons for Delay:Initially, the project received development permission for G+Stilt+7 floors. However, revised approval was granted for G+Stilt+8 floors. This adjustment necessita

Location, Land & Connectivity

Located at chandansar, kopri village road , Vasai, Palghar, 401305. Per the filed land record, the plot is bounded to the north by sani mandir, to the south by om sai siddhivinayak bldg, to the east by Kopri village road and to the west by metha pharma office. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~140 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park140 km
Andheri MIDC / SEEPZ141 km
Chhatrapati Shivaji Int'l Airport145 km
Bandra Kurla Complex (BKC)147 km
Lower Parel / Worli business district156 km
Nariman Point / Fort163 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Himali Construction is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other RERA-registered projects in Virar East

Viva Haritara Building-3/wing-B
Deregistered by MahaRERA · possession by Dec 2026 · Vivaholdings
Jivdani Mauli
Not filing quarterly progress reports · possession by Dec 2026 · Kiran Ramesh Patil
Mahavir Ashish CO-Operative Housing Society LTD
possession by Dec 2026 · Yashraj Developers
Raajlaxmi Avenue
possession by Dec 2026 · Magnus Infracon
Radheya Enterprises
possession by Dec 2026 · Divesh Ratilal Shah
SAI Baba Nagar
possession by Dec 2026 · VED Ganga

Other RERA-registered projects in Palghar

Ramchandra Sankul
declared completion Aug 2019 · Sai Rath Construction Co.
Ramesh Heights
possession by Dec 2026 · S S Enterprises
Ramesh Heights Phase 1
possession by Dec 2026 · SAI Vidya Construction
Ramesh Residency
possession by Dec 2026 · AAR AAR Homes India Private Limited
Rameshwar
declared completion Jul 2026 · Chheda Associate
Rameshwar Arcade
declared completion Dec 2025 · Level Up Realtors

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.