Mumbai/Project record

MahaRERA · the public record

RITE DEVANGI

BORIVALI WEST · YASHODANAND INFRA

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

0units filed as unsoldInventory · 19 September 2026
30 Oct 2025declared completionMahaRERA registration · read 12 Jul 2026
12registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Oct 2025

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800051848

Delivery and registration

When is the project declared for completion?

RITE DEVANGI is registered with MahaRERA as P51800051848 and the promoter has declared completion for 30 Oct 2025.

30 Oct 2025

declared completion

11months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800051848
Registered on07 Jul 2023
Promoter-declared completion30 Oct 2025
Current statusCertificate Signed
Against todayabout 11 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RITE DEVANGI record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Yashodanand Infra is the promoter of record on 5 projects registered with MahaRERA, none of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

0flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Construction

How much construction cost has been reported?

In RITE DEVANGI, ₹9.55 Cr of a declared ₹9.55 Cr estimated project cost is reported as incurred, about 100.0%, as at the last certified filing with MahaRERA.

100.0%

₹9.55 Cr

of ₹9.55 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In RITE DEVANGI, 10 of 10 homes filed with MahaRERA are recorded as sold or booked, about 100%, and 0 remain available.

100%sold

10 of 10 homes

₹11.15 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹11.15 Cr (about 100%) is recorded as collected and ₹0 as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 10 registered agreements, the effective carpet rate is ₹18,053/sqft, with eight in ten falling between ₹18,021 and ₹21,815 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

The inventory filing also declares: 2 reserved.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 10 homes carry one, and Every home on the filing is recorded sold or booked.

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet. This observation is an archived copy whose time is the moment the file was written, not a portal fetch time.

Every home in RITE DEVANGI is filed sold or booked, so there is no asking price left to test — but the record of what this project sold for is complete. The Price Comparison Report lists all 10 registered agreements: each home, its carpet area, the consideration filed against it and the rate that works out to. Built from the filing itself, sent by email.

See all 10 registered agreements — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+10 and 12 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
RITE DEVANGI1G+1012-

Unit mix on the filing: 12 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Oct 2025Due to shortage of material and labor not able to complete project please grant us extension till 30/10/2025

Location, Land & Connectivity

Located at BORIVALI WEST, TPS BORIVALI NO. I ,SITUATED AT PREM NAGAR , Andheri, Mumbai Suburban, 400092. Per the filed land record, the plot is bounded to the north by by land bearing CTS No 2413 10, to the south by Existing 9 mts Layout Road, to the east by by land bearing CTS Nos 2413 6 AND 2413 7 and to the west by Existing 9 mts Layout Road. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yashodanand Infra is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Yashodanand Infra

Yashodanand Infra
FlaggedMumbai Suburban

Other RERA-registered projects in Borivali West

Gopal Terrace Co-Operative Housing Society LTD
possession by Sep 2026 · Polo Infra Developers Private Limited
House Of Shreeji Sharan
possession by Sep 2026 · Miles Infra LLP
Sai Signature Spaces
possession by Sep 2026 · Ramachandran Munisawmy Narayan
Shikhhar
possession by Sep 2026 · Mahavir Land Developer
Swastik
possession by Sep 2026 · Reliance Corporation
Signet
possession by Oct 2026 · DG Builders

Major developers building in Borivali West

Other RERA-registered projects in Mumbai Suburban

Rite Divine
declared completion Dec 2018 · Rite Developers Pvt. Ltd.
Rite Luxuria
declared completion Dec 2019 · Rite Developers Pvt. Ltd.
Rite Nectar Phase II
declared completion Sep 2022 · Rite Developers Pvt. Ltd.
Rite Oscar
declared completion Jun 2021 · Rite Properties
Rite Perinto
declared completion Mar 2022 · Rite Developers Pvt. Ltd.
Rite Prime
declared completion Dec 2017 · Rite Developers Pvt. Ltd.

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026