MahaRERA Property Intelligence · Mumbai Suburban

Rite Divine

P51800006927 · promoter Rite Developers Pvt

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800006927
Registered on16 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rite Developers Pvt is the promoter of record on 48 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+41.

BuildingWingsFloorsDeclared completion
Rite Divine1G+4131 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 201831 Dec 2018We state that the said project got delayed due to delay in getting approval from MCGM for utilising available additional FSI to construct 4 flats on already constructed and approve

Location, Land & Connectivity

Located at Andheri, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by CTS NO 1159pt 1161 1162-1 1162-2 and 1163pt, to the south by CTS NO 1165 and 1169, to the east by CTS NO 1159 pt and 1160 pt and to the west by CTS NO 1163 pt and 1165 pt. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rite Developers Pvt. Ltd. is the promoter on 10 MahaRERA-registered projects, of which 10 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Rite Developers Pvt. Ltd. project & its RERA track record →

Other flagged projects by Rite Developers Pvt. Ltd.

Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban

Other RERA-registered projects in Kandivali West

Primrose
possession by Jul 2026 · Kaustubh Construction Private Limited
Harmony
possession by Aug 2026 · Shreenath Associates
Laxmi Heights
possession by Sep 2026 · M/S Laxmi Lifespaces
Mahavir Majesty
possession by Sep 2026 · Mahavir Builders
Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon

Major developers building in Kandivali West

Other RERA-registered projects in Mumbai Suburban

Rite Fortis
declared completion Mar 2023 · Rite Housing Developers
Rite Luxuria
declared completion Dec 2019 · Rite Developers Pvt. Ltd.
Rite Nectar Phase II
declared completion Sep 2022 · Rite Developers Pvt. Ltd.
Rite Oscar
declared completion Jun 2021 · Rite Properties
Rite Perinto
declared completion Mar 2022 · Rite Developers Pvt. Ltd.
Rite Prime
declared completion Dec 2017 · Rite Developers Pvt. Ltd.

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026