MahaRERA Property Intelligence · Mumbai Suburban

Rite Bliss

P51800007035 · Dahanukarwadi · promoter Rite Developers Pvt

Certificate SignedDue 31 Dec 2024

Delivery & Registration

MahaRERA registrationP51800007035
Registered on17 Aug 2017
Promoter-declared completion31 Dec 2024
Current statusCertificate Signed
Against todayabout 19 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Rite Developers Pvt is the promoter of record on 48 projects, of which 16 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
Rite Bliss1G+1431 Dec 2020

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000042896125/01/2024Ramnath Gangaram Kaloji vs Rite Developers Private Limitedorder passed

Legal & Litigation

The promoter has declared 1 court case on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
City Civil Dindoshi Court27632014Report On Settlement Matter Referred To Mediation

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202131 Dec 2024DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2024

Location, Land & Connectivity

Located at Dahanukarwadi, M G Road, Andheri, Mumbai Suburban, 400067. Per the filed land record, the plot is bounded to the north by By Public Road, to the south by By land bearing CTS No 874 part, to the east by By land bearing CTS No 874 part and to the west by By land bearing CTS No 876 A and 876 B part. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~9 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ9 km
Powai / Hiranandani business park12 km
Chhatrapati Shivaji Int'l Airport13 km
Bandra Kurla Complex (BKC)16 km
Lower Parel / Worli business district23 km
Nariman Point / Fort31 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Rite Developers Pvt. Ltd. is the promoter on 10 MahaRERA-registered projects, of which 10 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

See every Rite Developers Pvt. Ltd. project & its RERA track record →

Other flagged projects by Rite Developers Pvt. Ltd.

Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban
Rite Developers Pvt. Ltd.
Developer in insolvency (NCLT)Mumbai Suburban

Other RERA-registered projects in Kandivali West

Primrose
possession by Jul 2026 · Kaustubh Construction Private Limited
Harmony
possession by Aug 2026 · Shreenath Associates
Laxmi Heights
possession by Sep 2026 · M/S Laxmi Lifespaces
Mahavir Majesty
possession by Sep 2026 · Mahavir Builders
Neelam CHS LTD
possession by Sep 2026 · Sapriya Developers
Alok
possession by Sep 2026 · Shree Dhanesh Buildcon

Major developers building in Kandivali West

Other RERA-registered projects in Mumbai Suburban

Rite Celesta
declared completion Dec 2017 · Rite Developers Pvt. Ltd.
Rite Civis
declared completion Dec 2023 · Yashodanand Developers
Rite Devangi
declared completion Oct 2025 · Yashodanand Infra
Rite Divine
declared completion Dec 2018 · Rite Developers Pvt. Ltd.
Rite Fortis
declared completion Mar 2023 · Rite Housing Developers
Rite Luxuria
declared completion Dec 2019 · Rite Developers Pvt. Ltd.

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026