MahaRERA Property Intelligence · Mumbai Suburban

ROMELL EMPRESS C WING PHASE III - 18TH TO 22ND FLOOR

P51800025888 · BORIVALI WEST · promoter Romell Real Estate

Certificate SignedDue 30 Sep 2020

Delivery & Registration

MahaRERA registrationP51800025888
Registered on27 Jul 2020
Promoter-declared completion30 Sep 2020
Current statusCertificate Signed
Against todayabout 70 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Romell Real Estate is the promoter of record on 25 projects, of which 1 carries a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
ROMELL EMPRESS C WING PHASE III - 18TH TO 22ND FLOOR1G+530 Sep 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at BORIVALI WEST, EKSAR VILLAGE, I C COLONY, Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by CTS 929 WING AND WING B, to the east by CTS 927 and to the west by CTS 613 A. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Romell Real Estate Private Limited is the promoter on 15 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every Romell Real Estate Private Limited project & its RERA track record →

Other flagged projects by Romell Real Estate Private Limited

Romell Real Estate Private Limited
FlaggedMumbai Suburban
Romell Real Estate Private Limited
FlaggedMumbai Suburban
Romell Real Estate Private Limited
FlaggedMumbai Suburban
Romell Real Estate Private Limited
FlaggedMumbai Suburban
Romell Real Estate Private Limited
FlaggedMumbai Suburban
Romell Real Estate Private Limited
FlaggedMumbai Suburban

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Romell Espalier
possession by Dec 2030 · Romell Real Estate Private Limited
Romell Euphoria
declared completion Jun 2023 · Romell Real Estate Private Limited
Romell Myra
possession by Sep 2026 · Romell Properties Private Limited
Romell Orbis
possession by Sep 2026 · Romell Properties Private Limited
Romell Rhythm
declared completion Dec 2023 · Romell Real Estate Private Limited
Romell Serene
declared completion Mar 2025 · Romell Real Estate Private Limited

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026