Mumbai/Project record

MahaRERA · the public record

ROSWALT ZAIDEN

RAGHAVENDRA MANDIR ROAD JOGESHWERI WEST · A S HIGHTECH LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

291units filed as unsoldInventory · 19 September 2026
31 Dec 2028declared completionMahaRERA registration · read 12 Jul 2026
1,518registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2028

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800047680

Delivery and registration

When is the project declared for completion?

ROSWALT ZAIDEN is registered with MahaRERA as P51800047680 and the promoter has declared completion for 31 Dec 2028.

31 Dec 2028

declared completion

27months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800047680
Registered on17 Nov 2022
Promoter-declared completion31 Dec 2028
Current statusCertificate Signed
Against today27 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for ROSWALT ZAIDEN record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Construction

How much construction cost has been reported?

In ROSWALT ZAIDEN, ₹317.73 Cr of a declared ₹1296.30 Cr estimated project cost is reported as incurred, about 24.5%, as at the last certified filing with MahaRERA.

24.5%

₹317.73 Cr

of ₹1296.30 Cr declared cost

Cost incurred as last certified to MahaRERA. It is a financial measure, not a survey of site work, and it can lag on-site reality between filings.

Source · MahaRERA quarterly progress filing · read 12 Jul 2026

Sales

How much has actually been sold?

In ROSWALT ZAIDEN, 1,207 of 1,518 homes filed with MahaRERA are recorded as sold or booked (979 with registered agreements and 228 booked), about 80%, and 311 remain available.

80%sold

1,207 of 1,518 homes

₹1313.83 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹610.07 Cr (about 46%) is recorded as collected and ₹703.76 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 1207 registered agreements, the effective carpet rate is ₹22,290/sqft, with eight in ten falling between ₹18,389 and ₹25,479 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 19 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 1227 homes carry one, and 291 of the 1518 are recorded unsold. Since we started watching this ledger, 20 homes have moved out of the unsold list, most recently on 11 September 2026.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
202-ZEYA384 sqftRs 22,290 a sq ft typical, over Rs 17,895 to Rs 28,651660 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. One of the two observations is an archived copy whose time is the moment the file was written, not a portal fetch time.

In ROSWALT ZAIDEN, 219 of the 291 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 290 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+39 and 1518 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
ROSWALT ZYON1G+3362-
ROSWALT ZAIDEN A WING -SALE BUILDING NO 11G+39510-
ROSWALT ZAIDEN B WING- SALE BUILDING NO 11G+39318-
ROSWALT ZAIDEN C WING- SALE BUILDING NO 11G+39509-
ROSWALT ZEYA1G+23119-

Unit mix on the filing: 1422 residential and 96 non-residential (shops/offices).

Legal and disputes

What disputes are disclosed?

12 complaints are on the MahaRERA record for ROSWALT ZAIDEN, with orders passed in 0 of them.

12complaints

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1260209509/04/2026A S HIGHTECH LLP vs Sana Shahnawaz Ansaripending / no order on file
CC1260214711/04/2026A S HIGHTECH LLP vs SK Niyaz Alipending / no order on file
CC1260214811/04/2026A S HIGHTECH LLP vs Shahabuddin Iqbal Mandaipending / no order on file
CC1260355209/06/2026A S HIGHTECH LLP vs Mohammad Ali Mohammad Alam Pathanpending / no order on file
CC1260355309/06/2026A S HIGHTECH LLP vs Tayibali Jaminali Siddiquipending / no order on file
CC1260355409/06/2026A S HIGHTECH LLP vs Feroz Khanpending / no order on file
CC1260355609/06/2026A S HIGHTECH LLP vs Fatima Mushirahamad Shaikhpending / no order on file
CC1260355709/06/2026A S HIGHTECH LLP vs Mohammed Mustafa Dawood Dolipending / no order on file
CC1260393725/06/2026A S HIGHTECH LLP vs Ataur Rahaman Shaikhpending / no order on file
CC1260393925/06/2026A S HIGHTECH LLP vs Kavita Chauhanpending / no order on file
CC1260394025/06/2026A S HIGHTECH LLP vs Kavita Chauhanpending / no order on file
CC1260394125/06/2026A S HIGHTECH LLP vs Sangeetapending / no order on file

Location, Land & Connectivity

Located at RAGHAVENDRA MANDIR ROAD JOGESHWERI WEST, SINGH HOUSING COLONY S V ROAD, Andheri, Mumbai Suburban, 400102. Per the filed land record, the plot is bounded to the north by 20 MTR WIDE ROAD, to the south by 27 MTR DP ROAD, to the east by S V ROAD and to the west by 12 WIDE D P ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport6 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district15 km
Nariman Point / Fort23 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Royal Accord
declared completion Dec 2025 · Viva Homes Private Limited
Royal Altezza
declared completion Aug 2026 · Shri Ganesh Developers
Royal Bliss
possession by Dec 2027 · Royal Developers
Royal Crystal Wing B
declared completion Dec 2021 · Royal Realtors
Royal Eksar
declared completion Apr 2026 · Kosmos Developers
Royal Fantasy Phase II
possession by Dec 2026 · Royal Fantasy Constructions Private Limi

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026