Mumbai/Project record

MahaRERA · the public record

RUBI PARK

Thane · IFTEKHAR KAMRUDDIN KHAN

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Sep 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Sep 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000013619

Delivery and registration

When is the project declared for completion?

RUBI PARK is registered with MahaRERA as P52000013619 and the promoter has declared completion for 30 Sep 2023.

30 Sep 2023

declared completion

36months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000013619
Registered on16 Oct 2017
Promoter-declared completion30 Sep 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUBI PARK record 24 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 24 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Iftekhar Kamruddin Khan is the promoter of record on 5 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RUBI PARK in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+6.

BuildingWingsFloorsDeclared completion
RUBY PARK1G+630 Sep 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Sep 2023COVID -19 PANDAMICS AND SUBSEQUENT NATIONWIDE LOCKDOWN AND NON AVAILABILITY OF WORKERS AND MATERIALSDUE TO LOCKDOWN AND DURING THIS PERIOD NO SLAES RAISED SO FUND ISSUE RAISED SO

Location, Land & Connectivity

Located at Thane, Thane, 410101. Per the filed land record, the plot is bounded to the north by PLOT NO 2, to the south by HISSA NO 18, to the east by HISSA NO 14 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~47 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park47 km
Bandra Kurla Complex (BKC)49 km
Chhatrapati Shivaji Int'l Airport50 km
Andheri MIDC / SEEPZ51 km
Lower Parel / Worli business district52 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Neral

Arsh Apartment
possession by Sep 2026 · Mateen Rafique Patel
Naaz Plaza
possession by Sep 2026 · Prestige Reality
Labdhi Gardens Phase 6
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 7
possession by Dec 2026 · Labdhi Lifestyle Limited
Labdhi Gardens Phase 8
possession by Dec 2026 · Labdhi Lifestyle Limited
RAJ Baug Phase - III
possession by Dec 2026 · Nehaldhara Realtors

Major developers building in Neral

Other RERA-registered projects in Raigarh

Ruby Corner
declared completion Sep 2021 · Tauseef Shamshulhuda Khan
Ruby Enclave
declared completion Jun 2021 · S. H. K. Developers
Rudra Bhalchandra
possession by Feb 2029 · Sitaram Janardan Hudar
Rudra Dhumravarna
possession by Jan 2028 · Sitaram Janardan Huddar
Rudra Dream City
possession by Jun 2030 · SAI Ashirwad
Rudra Empire
possession by Dec 2028 · Shree SAI Infra

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026