MahaRERA · the public record
RUBY CORNER
ULWE, RAIGAD · TAUSEEF SHAMSHULHUDA KHAN
Know the project.
Then choose your home.
The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.
The record · free to read
Registration read 12 Jul 2026Progress & dates
The timeline on file.
Available record
No construction trend to plot.
The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.
declared completion
30 Sep 2021
The registered date and a construction update answer different questions. Neither is a confirmation of possession.
MahaRERA registration · read 12 Jul 2026
From another project
See the report before you buy.
A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.
Read a sample report ↗The source record
The details behind the headline.
MahaRERA · P52000029369
Delivery and registration
When is the project declared for completion?
RUBY CORNER is registered with MahaRERA as P52000029369 and the promoter has declared completion for 30 Sep 2021.
30 Sep 2021
declared completion
60months past
against the declared date
The completion date and status as they stand on the MahaRERA registration record.
Source · MahaRERA project registration · read 12 Jul 2026
| MahaRERA registration | P52000029369 |
| Registered on | 29 May 2021 |
| Promoter-declared completion | 30 Sep 2021 |
| Current status | Certificate Signed |
| Against today | about 60 months past the declared date |
Approvals and compliance
What compliance filings are on record?
MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUBY CORNER record 2 quarterly progress reports since registration.
2quarterly filings
Entries as they appear on MahaRERA's own lists and the project's progress filing.
Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026
- Filing progress reports — 2 quarterly progress reports on record since registration, with no current default.
Sales
Are registered sale-agreement prices available?
No registered sale-agreement price is recorded for RUBY CORNER in the MahaRERA project file.
Not available
This is what the record does not contain, not a value of zero.
Source · MahaRERA project file · checked 12 Jul 2026
Buildings & Wings
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.
| Building | Wings | Floors | Declared completion |
|---|---|---|---|
| RUBY CORNER | 1 | G+5 | 30 Sep 2021 |
Complaints
No buyer complaints were on this project's MahaRERA record at the time of reading.
Deadline Extensions
The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.
| From | Extended to | Stated reason |
|---|---|---|
| as registered | 30 Sep 2022 | Due to (COVID-19) Pandemic, the balance physical work is going to take 4 to 6 months. kindly grant us the extension of 12 months |
Location, Land & Connectivity
Located at ULWE, RAIGAD, SECTOR-8, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by B-94, to the south by 11 M WIDE ROAD, to the east by 11 M WIDE ROAD and to the west by PLOT NO 110. These are the boundaries as recorded in the filed land record.