Mumbai/Project record

MahaRERA · the public record

RUKMINI ENCLAVE

BOISER EAST · ADITI BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000021813

Delivery and registration

When is the project declared for completion?

RUKMINI ENCLAVE is registered with MahaRERA as P99000021813 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000021813
Registered on29 Jul 2019
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for RUKMINI ENCLAVE record 28 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Aditi Builders Developers is the promoter of record on 26 projects registered with MahaRERA, 5 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

26projects

registered with MahaRERA

5flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for RUKMINI ENCLAVE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
RUKMINI ENCLAVE BUILDING NO 4 WING C1G+430 Jun 2022
RUKMINI ENCLAVE BUILDING NO 4 WING D1G+430 Jun 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2026we need some more time period for construction and completion work of our project, so we are applying for extension

Location, Land & Connectivity

Located at BOISER EAST, TATA HOUSING ROAD, Vasai, Palghar, 401501. Per the filed land record, the plot is bounded to the north by 12M WIDE ROAD, to the south by OPEN SPACE, to the east by BUILDING NO 6 and to the west by BUILDING NO 4 WING A AND B. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~140 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park140 km
Andheri MIDC / SEEPZ141 km
Chhatrapati Shivaji Int'l Airport145 km
Bandra Kurla Complex (BKC)147 km
Lower Parel / Worli business district156 km
Nariman Point / Fort163 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Aditi Builders & Developers is the promoter on 2 MahaRERA-registered projects, of which 2 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Aditi Builders & Developers

Aditi Builders & Developers
Not filing quarterly progress reportsPalghar

Other RERA-registered projects in Boisar

Classic Apartment
possession by Sep 2026 · I.k.group
Divyajal
possession by Sep 2026 · Divyaraj Properties LLP
Kinjal Complex II
possession by Sep 2026 · Kinjal Enterprises
Queens Villa - 2
possession by Sep 2026 · Super Realty
Marathe Complex
possession by Dec 2026 · Gprs Realty
Rajhans United Regency III
possession by Dec 2026 · Rajhans Homes

Other RERA-registered projects in Palghar

Rushi Vihar NX
possession by Dec 2030 · Not Available
Ruturaj Classic
possession by Dec 2030 · Ruturaj Realtors
Ruturaj Garden
possession by Dec 2032 · Ruturaj Squares
Ruturaj Homes
possession by Dec 2030 · Ruturaj Homes
Ruturaj Squares
declared completion Jan 2026 · Ruturaj Squares
S.K Heights
possession by Jun 2027 · Shahzada Sultan Khan

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026