SABARI SHAAN

P51800010056 · mumbai · promoter Shankheshwar Properties Pvt

Certificate SignedDue 31 Dec 2018

Delivery & Registration

MahaRERA registrationP51800010056
Registered on23 Aug 2017
Promoter-declared completion31 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shankheshwar Properties Pvt is the promoter of record on 16 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+22.

BuildingWingsFloorsDeclared completion
SABARI SHAAN1G+2231 Dec 2018

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000019389702/09/2020Shankheshwar Properties Pvt. Ltd. vs Anil Maruti Chavanorder passed

Location, Land & Connectivity

Located at mumbai, chembur, Kurla, Mumbai Suburban, 400074. Per the filed land record, the plot is bounded to the north by CTS No 311 and 317, to the south by Marvali Church Road, to the east by CTS No 313 and 312 and to the west by Mhata School. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~5 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)5 km
Lower Parel / Worli business district7 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park10 km
Andheri MIDC / SEEPZ11 km
Nariman Point / Fort13 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Chembur

Satwaratna Co Op Hsg Society Ltd
possession by Sep 2026 · Kishrajdevelopers
Bhagwan Residency
possession by Oct 2026 · V3 Partners
Safal Ganga Smruti
possession by Nov 2026 · Varun Homes PVT LTD
Jade Residences
possession by Dec 2026 · JSR Realty
SAI Orion
possession by Dec 2026 · Vineet Buildcon Private Limited
D J Nest
possession by Mar 2027 · Dhiraj Narayandas Jadhwani

Other RERA-registered projects in Mumbai Suburban

Sabari Shobha
declared completion Nov 2021 · Sabari Developers LLP
Sach Splendid
possession by Apr 2027 · Sach Realtors
Sadakamal Co-Operative Housing Society Limited
declared completion Dec 2022 · Haritara Construction Company
Sadasukh
possession by Mar 2027 · Shree Vighnaharta Lifespace LLP
Sadguru Avenue
possession by Dec 2026 · Sadguru Krupa Developers
Sadguru Avighna
possession by Dec 2027 · Sadgurur Kreepa Developer

What to verify (NCLT insolvency)

  1. Check the IRP/Resolution Professional's name on the NCLT cause list and contact them for a project status update.
  2. Verify whether a Resolution Plan has been approved — the IRP's report is filed with NCLT and is public.
  3. Look for a homebuyers' association for this project — allottee groups have legal standing in insolvency proceedings.
  4. Consult a RERA or IBC advocate about your rights under Section 7 IBC or Section 18 RERA for possession or refund.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026