P51700013099 · Murbad · promoter Nirman Developers

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP51700013099
Registered on14 Sep 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Sales & Inventory

Of 82 homes filed with MahaRERA, 12 are sold/booked and 70 remain available (~15% sold) — early in sales — more choice of units now, but confirm the developer has the pre-sales to fund the build. Buyers have committed ₹1.20 Cr in agreement value so far. Of that, ₹1.11 Cr (~92%) is already collected, ₹0 receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 12 registered agreements, the effective carpet rate is ₹3,456/sqft (typical range ₹3,456–₹3,456) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8 and 82 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
BUILDING 41G+54031 Dec 2021
BUILDING 7/A1G+84231 Dec 2021

Unit mix on the filing: 80 residential and 2 non-residential (shops/offices).

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Dec 202230 Dec 2023As you are aware, there was complete site closure from March 2020 till September 2020 due to Covid-19. Thereafter also we could not start the work in full swing due to a shortage o

Location, Land & Connectivity

Located at Murbad, Murbad, Murbad, Thane, 421401. Per the filed land record, the plot is bounded to the north by Survey No 44-3-2 64-6, to the south by Survey No 66 65-6, to the east by Survey No 65-5 64-7 64-6 and attach road and to the west by Survey No 77-1. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~54 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park54 km
Andheri MIDC / SEEPZ57 km
Chhatrapati Shivaji Int'l Airport58 km
Bandra Kurla Complex (BKC)59 km
Lower Parel / Worli business district66 km
Nariman Point / Fort70 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

See every M/S Nirman Developers project & its RERA track record →

Other RERA-registered projects in Murbad

Shree Siddhivinayak Park C1,c2,c3
Not filing quarterly progress reports · possession by Dec 2026 · Satyashiv Developers
Madhusudan Retreat Terraces
possession by Dec 2026 · Madhusudan Leisure Homes
OM Shree SAI Villa
possession by Dec 2026 · Not Available
SAI Krishna Heights
possession by Dec 2026 · OM SAI Developers
SAI Krupa Apartment
possession by Dec 2026 · Bhimraj Ganpat More
Sarosh Complex
possession by Dec 2026 · Sarosh Imran Kohari

Other RERA-registered projects in Thane

Sahyadri Villas
declared completion Nov 2019 · Ashoka Dreams Developers
Sahyog IBM
declared completion Dec 2024 · S S Construction
SAI Aangan
declared completion Jan 2023 · Pinnacle Realtors
SAI Aangan - C Wing
declared completion Dec 2018 · Shree SAI Chatra Developers
SAI Aashiyana - II
declared completion Jun 2026 · Sai Sakshi Developers
SAI Abhishek Chsl
possession by Mar 2029 · Aristone Developments

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026