MahaRERA Property Intelligence · Thane

Sai Arcade

P51700003993 · PHADKE ROAD DOMBIVLI EAST · promoter Sai Mangal Enterprises

Certificate SignedDue 30 Sep 2025

Delivery & Registration

MahaRERA registrationP51700003993
Registered on07 Aug 2017
Promoter-declared completion30 Sep 2025
Current statusCertificate Signed
Against todayabout 10 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sai Mangal Enterprises is the promoter of record on 173 projects, of which 25 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
A Wing1G+1031 Dec 2020
WING B1G+1431 Dec 2020
Proposed not sanctioned1--

Complaints & Orders

1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000022082815/04/2022malhar darshan society vs SAI MANGAL ENTERPRISESorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 3 times. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Sep 202530 Dec 2022THERE IS A MATERAIL SHORTAGE SIMULTENEOUSLY LABOUR ALSO SHORTAGE DUE TO PANDEMIC CITUALTION OF COVID 19 PROKJECT WORK IS SLOW DUE TO MAIN REASON PROJECT IS NOT YET COMPLTED WE NEED
30 Sep 202530 Sep 2025SHORTAGE OF MATERIAL AND LABOUR
30 Sep 202531 Mar 2024a

Location, Land & Connectivity

Located at PHADKE ROAD DOMBIVLI EAST, GANPATI MANDIR CROSS ROAD , Kalyan, Thane, 421201. Per the filed land record, the plot is bounded to the north by HARI CHAYA CHS, to the south by 15 MTR D P ROAD, to the east by SHREE JALARAM ASHISH SOCIETY and to the west by DEDHIA NIWAS CHS. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~27 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park27 km
Andheri MIDC / SEEPZ30 km
Chhatrapati Shivaji Int'l Airport32 km
Bandra Kurla Complex (BKC)33 km
Lower Parel / Worli business district41 km
Nariman Point / Fort47 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Dombivli East

Premsadan CHS
possession by Jul 2026 · Namrata Realtors
OM Trimurti Darshan
possession by Aug 2026 · Prachi Group
Pannash
possession by Aug 2026 · Technicon
Rashmi Priya CO-OP HSG SOC LTD
possession by Aug 2026 · Shree Riddhi Siddhi Infraproject
Mahalaxmi Ashish D Wing
possession by Sep 2026 · Swastik Enterprises
NAV Pratima CO. OP. Hsg. Soc. LTD
possession by Sep 2026 · Narendra Kalyanji Patel

Major developers building in Dombivli East

Other RERA-registered projects in Thane

SAI Arcade
declared completion Dec 2017 · SAI Developers
SAI Arcade
declared completion Jul 2019 · Saiprasad Enterprises
SAI Arcade
declared completion Dec 2025 · OM SAI Developers
SAI Arcade
possession by Dec 2027 · Ganesh Developers
SAI Arcade
possession by Dec 2028 · SAI Siddhi Enterprises
SAI Arpan
declared completion Mar 2024 · SAI Builder AND Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026