MahaRERA Property Intelligence · Thane

SAI KANISHK PHASE I

P51700006847 · promoter Om Sai Infra

Certificate SignedDue 31 May 2018

Delivery & Registration

MahaRERA registrationP51700006847
Registered on16 Aug 2017
Promoter-declared completion31 May 2018
Current statusCertificate Signed
Against todayabout 98 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Om Sai Infra is the promoter of record on 5 projects, of which none currently carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
B11G+8-
B21G+831 May 2018
B31G+8-

Complaints & Orders

9 complaints are on the MahaRERA record for this project, with orders passed in 9. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.

Complaint no.FiledPartiesStatus
CC00600000000025122/08/2017KAPURCHAND RAJARAM GUPTA vs SAI KANISHKorder passed
CC00600000000084625/09/2017VIJAYKUMAR SHRINATH GUPTA vs OM SAI INFRA AND OM SAI GROUPorder passed
CC00600000007925011/05/2019Sunil K Gala vs Om Sai Infra and Om Sai Grouporder passed
CC00600000005459925/05/2018PRAVIN PATEL vs MAHESH PATELorder passed
CC00600000005588016/10/2018PRAVIN PATEL vs MAHESH PATELorder passed
CC00600000005759009/01/2019PRAVIN PATEL vs MAHESH PATELorder passed
CC00600000005465126/05/2018Jatinder kaur chand sohal vs OM SAI INFRA MAHESH PATELorder passed
CC00600000005745226/12/2018MANSI MANOHAR MUNDADA vs MAHESH PATELorder passed
CC00600000019352018/07/2020A.K. ENTERPRISES vs OM SAI INFRA & OM SAI GROUPorder passed

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 May 201831 May 2018CONSTRUCTION IS COMPLETED, TRANSFORMER TO BE INSTALLED AND LICENSE FROM PWD FOR OPERATING OF LIFTS IS AWAITED

Location, Land & Connectivity

Located at Thane, Thane, 400612. Per the filed land record, the plot is bounded to the north by PLOT BEARING NO 5 HISSA NO 11, to the south by PLOT BEARING NO 5 HISSA NO 4, to the east by PLOT BEARING NO 5 HISSA NO 3 and to the west by PLOT NO 5 HISSA NO 6. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~16 km away — a real but liveable commute to the nearest job hub — factor peak-hour traffic.

LandmarkStraight-line
Powai / Hiranandani business park16 km
Andheri MIDC / SEEPZ19 km
Chhatrapati Shivaji Int'l Airport21 km
Bandra Kurla Complex (BKC)21 km
Lower Parel / Worli business district29 km
Nariman Point / Fort35 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Om Sai Infra & Om Sai Group is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Om Sai Infra & Om Sai Group

Om Sai Infra & Om Sai Group
FlaggedThane

Other RERA-registered projects in Mumbra

Celosia Avenue
possession by Sep 2026 · Pratima Construction
Quality Annex
possession by Sep 2026 · Quality Annex
YES Central Galleria
possession by Oct 2026 · Noble Enterprises
YES Central Galleria 1
possession by Oct 2026 · YES Enterprises
Sagar Enclave
possession by Dec 2026 · Kanchan Builders & Developers
Grace Square Type D3
possession by Dec 2026 · Shree Sumatinath Enterprises LLP

Major developers building in Mumbra

Other RERA-registered projects in Thane

SAI Kanishk Phase II
declared completion Jun 2025 · Om Sai Infra & Om Sai Group
SAI Karishma Enclave
declared completion Dec 2023 · Suresh Radheshyam Kabra
SAI Kishan Apartment
declared completion Jul 2019 · SAI Kishan Constructions
SAI Kripa Residency
declared completion Apr 2024 · Gokuldham Builders & Developers
Sai Krishna
possession by Dec 2026 · Manish Prakash Mutha
SAI Krishna Heights
possession by Dec 2026 · OM SAI Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026