SAI NIWAS CO OP HSG SOC LTD

NALLASOPARA WEST · G R SONS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 May 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 May 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000030381

Delivery and registration

When is the project declared for completion?

SAI NIWAS CO OP HSG SOC LTD is registered with MahaRERA as P99000030381 and the promoter has declared completion for 31 May 2024.

31 May 2024

declared completion

28months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000030381
Registered on17 Aug 2021
Promoter-declared completion31 May 2024
Current statusCertificate Signed
Against todayabout 28 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI NIWAS CO OP HSG SOC LTD record 12 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 12 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sons is the promoter of record on 119 projects registered with MahaRERA, 13 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

119projects

registered with MahaRERA

13flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI NIWAS CO OP HSG SOC LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAI NIWAS CO OP HSG SOC LTD1G+431 May 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at NALLASOPARA WEST , S T DEPOT , AMI PARK ROAD, Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by SAI POOJA BUILDING and to the west by MUKTI SAGAR. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Kunal Height
possession by Dec 2026 · Shree SAI Builders & Developers
Vimal Classic
possession by Dec 2026 · OM Vimal Developers
Anant Tower E AND F
possession by Dec 2026 · Shantinath Enterprises
Dhananjay Avenue
possession by Dec 2026 · SAI Kiran Builder AND Developers
Sai Baba Nagar Residential With Shopline Building With A B C Wings
Not filing quarterly progress reports · possession by Dec 2026 · Shreeji Associates

Other RERA-registered projects in Palghar

SAI Park
declared completion Dec 2023 · Kamlesh Kantilal Pipaliya
SAI Park
possession by Sep 2026 · OM Siddhivinayak Developers
SAI Plaza
declared completion Apr 2022 · OM SAI Builders AND Developers
SAI Pooja Apartment
declared completion Oct 2024 · SAI Pooja Enterprises
SAI Pooja Apartment Building NO. 7 Wing -B
possession by Mar 2027 · Shreeya Developers
SAI Prasad Apartment
possession by Dec 2026 · Vinod Motiram Pawar

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026