MahaRERA Property Intelligence · Palghar

SAI NIWAS CO OP HSG SOC LTD

P99000030381 · NALLASOPARA WEST · promoter Sons

Certificate SignedDue 31 May 2024

Delivery & Registration

MahaRERA registrationP99000030381
Registered on17 Aug 2021
Promoter-declared completion31 May 2024
Current statusCertificate Signed
Against todayabout 26 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Sons is the promoter of record on 112 projects, of which 13 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SAI NIWAS CO OP HSG SOC LTD1G+431 May 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at NALLASOPARA WEST , S T DEPOT , AMI PARK ROAD, Vasai, Palghar, 401203. Per the filed land record, the plot is bounded to the north by ROAD, to the south by ROAD, to the east by SAI POOJA BUILDING and to the west by MUKTI SAGAR. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nallasopara West

Rameshwar
possession by Jul 2026 · Chheda Associate
Shalibhadra Yash
possession by Jul 2026 · Sumatinath Builders
Unique Avenue 210
possession by Aug 2026 · Mangalmurti Land Developers
Shree Ganesh Krupa Residency
possession by Sep 2026 · Nutan Construction CO
Kaneri Heights
possession by Sep 2026 · Shekhar Bhoir AND Others
Aleen Heights
possession by Nov 2026 · AB Builders AND Developers

Other RERA-registered projects in Palghar

Sai Paradise
declared completion Nov 2018 · Sai Paradise
SAI Parivar
declared completion Jan 2021 · SAI Parivar Construction Company
SAI Park
declared completion May 2022 · Decimus Realty LLP
SAI Plaza
declared completion Apr 2022 · OM SAI Builders AND Developers
SAI Pooja Apartment
declared completion Oct 2024 · SAI Pooja Enterprises
SAI Pooja Apartment Building NO. 7 Wing -B
possession by Mar 2027 · Shreeya Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026