Mumbai/Project record

MahaRERA · the public record

SAI SANSAR RESIDENCY

Thane · ARUN BALU PATIL

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700008197

Delivery and registration

When is the project declared for completion?

SAI SANSAR RESIDENCY is registered with MahaRERA as P51700008197 and the promoter has declared completion for 30 Dec 2022.

30 Dec 2022

declared completion

45months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700008197
Registered on18 Aug 2017
Promoter-declared completion30 Dec 2022
Current statusCertificate Signed
Against todayabout 45 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAI SANSAR RESIDENCY record 22 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 22 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAI SANSAR RESIDENCY in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
BUILDING NO 41G+831 Dec 2020
BUILDING NO 61G+831 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered30 Jun 2022Due to scarcity of Labour & Material in Covid Period our construction work was stopped for 6 to 8 months.

Location, Land & Connectivity

Located at Kalyan, Thane, 421401. Per the filed land record, the plot is bounded to the north by GUT NO 115 AND GUT NO 125, to the south by PROPERTY OF SHRI KARALE AND GUT NO 115, to the east by GUT NO 125 AND GUT NO 126 and to the west by INTERNAL ROAD OF SAISAGAR RESIDENCY AND GUT NO 123. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~53 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park53 km
Andheri MIDC / SEEPZ57 km
Chhatrapati Shivaji Int'l Airport58 km
Bandra Kurla Complex (BKC)59 km
Lower Parel / Worli business district66 km
Nariman Point / Fort70 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Arun Balu Patil is the promoter on 4 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Arun Balu Patil

Other RERA-registered projects in Murbad

Shree Siddhivinayak Park C1,c2,c3
Not filing quarterly progress reports · possession by Dec 2026 · Satyashiv Developers
Arjun Heights
Not filing quarterly progress reports · possession by Dec 2026 · Nanda Arjun Shelke
Madhusudan Retreat Terraces
possession by Dec 2026 · Madhusudan Leisure Homes
SAI Krishna Heights
possession by Dec 2026 · OM SAI Developers
Swami Narendra Residency
possession by Dec 2026 · RAJ Ratneshwari Developers
Techcons Basera
possession by Dec 2026 · Techcons Constructional Engineering Co

Other RERA-registered projects in Thane

SAI Satyam Residency B Building
declared completion Dec 2024 · SAI Satyam Group
SAI Sharada CHS LTD
declared completion May 2026 · M Square Developers
SAI Sheetal Apartment
possession by Jan 2027 · Sagar Ganesh Kadav
Sai Shraddha
declared completion Jul 2019 · Shreesai Developers
SAI Shraddha
declared completion Dec 2023 · Dhulchand Shankar Naik
SAI Shrushti Leela
possession by Dec 2027 · SAI Shrushti Enterprises

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026