MahaRERA Property Intelligence · Raigarh

SAI YOG

P52000010605 · promoter Criinfra

Certificate SignedDue 30 Dec 2023

Delivery & Registration

MahaRERA registrationP52000010605
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2023
Current statusCertificate Signed
Against todayabout 31 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5.

BuildingWingsFloorsDeclared completion
SAI YOG1G+531 Dec 2022

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Mahad, Raigarh, 402301. Per the filed land record, the plot is bounded to the north by SURVEY NUMBER 81-13B, to the south by MUMBAI-GOA HIGHWAY, to the east by SURVEY NUMBER 83-15 and to the west by SURVEY NUMBER 81-4 PART. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~119 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort113 km
Lower Parel / Worli business district119 km
Bandra Kurla Complex (BKC)124 km
Chhatrapati Shivaji Int'l Airport126 km
Powai / Hiranandani business park127 km
Andheri MIDC / SEEPZ130 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Mahad

Chandrabhaga Residency
possession by Dec 2026 · Rajesh Namdev Pawale
Herai Complex - B Wing, Hajwane Complex- C Wing
possession by Dec 2026 · Akhtar Ahmed Lambade
Raigad City
possession by Dec 2026 · Dhanalaxmi Realtors
SAI Nandanvan
possession by Dec 2026 · Stuti Developers
Vedika Hills
Not filing quarterly progress reports · possession by Dec 2026 · Rajendra Mehetar Krishana
Aditi Apartment
possession by Dec 2026 · Aijaz Ismail Darekhan

Other RERA-registered projects in Raigarh

Saiccha Park
possession by Dec 2027 · Kasheenath Ganpat Lotnkar
Saichaitanya
possession by Dec 2026 · Bhosale Buildcon
Saidham
declared completion May 2022 · Anil Pandurang Mungaji
Saikrupa
declared completion Dec 2021 · Vaishnavi Associates Builders & Deve
Saikunj CO-Operative HSG Society
declared completion May 2024 · Royal Enterprises
Saileela
declared completion Dec 2019 · Dennis James Fernandes

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026