Mumbai/Project record

MahaRERA · the public record

SAMIRA PAVILIONS

Mumbai City · SAMIRA REALTY PROJECTS PRIVATE LIMITED

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000010155

Delivery and registration

When is the project declared for completion?

SAMIRA PAVILIONS is registered with MahaRERA as P52000010155 and the promoter has declared completion for 31 Dec 2019.

31 Dec 2019

declared completion

81months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000010155
Registered on24 Aug 2017
Promoter-declared completion31 Dec 2019
Current statusCertificate Signed
Against todayabout 81 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAMIRA PAVILIONS record 10 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 10 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Samira Realty Projects is the promoter of record on 2 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAMIRA PAVILIONS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1.

BuildingWingsFloorsDeclared completion
A1/11G+1-
A1/21G+1-
A1/31G+1-
A1/41G+1-
A3/11G+1-
A3/21G+1-
A3/31G+1-
A3/41G+1-
A6/11G+1-
A6/21G+1-
A6/31G+1-
A6/41G+1-
B2/11G+1-
B2/21G+1-
B2/31G+1-
B2/41G+1-
B3/11G+1-
B3/21G+1-
B3/31G+1-
B3/41G+1-
B4/11G+1-
B4/21G+1-
B4/31G+1-
B4/41G+1-
B5/11G+1-
B5/21G+1-
B5/31G+1-
B5/41G+1-
B6/11G+1-
B6/21G+1-
B6/31G+1-
B6/41G+1-
C31G+1-

Legal and disputes

What disputes are disclosed?

6 complaints are on the MahaRERA record for SAMIRA PAVILIONS, with orders passed in 6 of them.

6complaints

6with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC00600000020944817/12/2021Heetesh Kalyanji Veera vs Samira Realty Projects Pvt. Ltd.order passed
CC00600000005768029/01/2019Dr. Sunil Wagh vs Samira Realty Projects Private Limitedorder passed
CC00600000005779031/01/2019Dr. Vimal Someshwar vs Samira Realty Projects Private Limitedorder passed
CC00600000005779105/03/2019Dr. Domnic D'Silva vs Samira Realty Projects Private Limitedorder passed
CC00600000019308624/03/2020Jyoti Devjani vs Samira Realty Pvt Ltdorder passed
CC00600000019639922/03/2021Kaumudi Vohera vs Samira Realty Projects Pvt Ltdorder passed

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. 2 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Consumer Disputes Redressal Commission Maharashtra State At Mumbai3092017Pending
Consumer Disputes Redressal Commission Maharashtra State At Mumbai2102017Pending

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2019Income tax attachment of bank accounts

Location, Land & Connectivity

Located at Mumbai City, Mumbai City, 402204. Per the filed land record, the plot is bounded to the north by GAT NUMBER 1726 AND OTHERS, to the south by GAT NUMBER 1751, to the east by GAT NUMBER 1744 AND 1726 and to the west by GAT NUMBER 1758. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~43 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Nariman Point / Fort36 km
Lower Parel / Worli business district43 km
Bandra Kurla Complex (BKC)50 km
Chhatrapati Shivaji Int'l Airport53 km
Powai / Hiranandani business park56 km
Andheri MIDC / SEEPZ57 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Nagaon

Nilaya
possession by Dec 2026 · Fourthstreet Consultancy LLP
Suki-Nihon-Phase 2
possession by Jun 2027 · Nimesh Kirti Chhatbar
Coral Bay
possession by Dec 2028 · Dynamix Vacation Resorts Private Limited
Coral Court
possession by Dec 2028 · Dynamix Vacation Resorts Private Limited
Coral Nest
possession by Dec 2028 · Dynamix Vacation Resorts Private Limited
Creata Harmony
possession by Dec 2028 · Creata Lifespaces Llp

Major developers building in Nagaon

Other RERA-registered projects in Raigarh

Samruddhi Enclave
declared completion Jun 2024 · Samruddhi Enterprises
Samruddhi Green View
possession by Dec 2030 · Ajinkya Tushar More
Sandhya Sadan
possession by Dec 2026 · Sujit Janardhan Mhatre
Sankalp Meadows
declared completion Jun 2025 · NEW Path Developers LLP
Sansaaraa
possession by Jun 2028 · SAI Darshan
Sanskruti
possession by Sep 2026 · Sandip Shankar Patil

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026