MahaRERA Property Intelligence · Mumbai City
P51900026345 · Nadkarni Park · promoter Sanghvi Premises Private
| MahaRERA registration | P51900026345 |
| Registered on | 11 Sep 2020 |
| Promoter-declared completion | 30 Jun 2025 |
| Current status | Certificate Signed |
| Against today | about 13 months past the declared date |
MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.
Across MahaRERA, Sanghvi Premises Private is the promoter of record on 45 projects, of which 4 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.
Of 31 homes filed with MahaRERA, 19 are sold/booked and 12 remain available (~61% sold) — selling steadily. Buyers have committed ₹33.52 Cr in agreement value so far. Of that, ₹30.23 Cr (~90%) is already collected, ₹3.29 Cr receivable — a read on how far along these sales really are. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.
What buyers actually paid: across 19 registered agreements, the effective carpet rate is ₹26,786/sqft (typical range ₹25,461–₹29,263) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.
The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:
| Floor | Unit | Carpet | Reckoner value |
|---|---|---|---|
| Floor 16 | A-1602 | 844 sqft (78.45 sqm) | ₹1.91 Cr |
| Floor 17 | A-1702 | 844 sqft (78.45 sqm) | ₹1.91 Cr |
| Floor 19 | A-1901 | 603 sqft (56 sqm) | ₹1.37 Cr |
| Floor 19 | A-1903 | 591 sqft (54.95 sqm) | ₹1.34 Cr |
| Floor 19 | A-1904 | 592 sqft (54.99 sqm) | ₹1.34 Cr |
| Floor 20 | A-2002 | 844 sqft (78.45 sqm) | ₹1.91 Cr |
| Floor 20 | A-2004 | 592 sqft (54.99 sqm) | ₹1.34 Cr |
| Floor 21 | A-2102 | 844 sqft (78.45 sqm) | ₹1.91 Cr |
| Floor 21 | A-2103 | 591 sqft (54.95 sqm) | ₹1.34 Cr |
| Floor 21 | A-2104 | 592 sqft (54.99 sqm) | ₹1.34 Cr |
| Floor 22 | A-2203 | 591 sqft (54.95 sqm) | ₹1.34 Cr |
| Floor 22 | A-2204 | 592 sqft (54.99 sqm) | ₹1.34 Cr |
No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing — still confirm your specific unit's status in the agreement.
The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7 and 31 homes are registered across the project.
| Building | Wings | Floors | Homes | Declared completion |
|---|---|---|---|---|
| Sanghvi Heights Phase 2 | 1 | G+7 | 31 | - |
Unit mix on the filing: 31 residential.
1 complaint is on the MahaRERA record for this project, with orders passed in 1. An adjudicated complaint is the clearest evidence of how this promoter behaves when pushed — read the orders in full.
| Complaint no. | Filed | Parties | Status |
|---|---|---|---|
| CC12400233 | 26/09/2024 | Tasneem Feroz Nalwalla vs Sanghvi Premises Private Limited | order passed |
The promoter has declared 6 court cases on this project to MahaRERA. 6 are still pending. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your flat. This is declared by the promoter; there may be further cases not on the RERA record.
| Court | Case no. | Year | Status |
|---|---|---|---|
| Bombay High Court | Criminal Writ Petition No 2091 | 2014 | Pending |
| Bombay High Court | SC Suit No 1757 of 2016 | 2016 | Pending |
| Bhoiwada Court Dadar Mumbai | CC NO 193 SW | 2013 | Pending |
| The Honble High Power Committee At Mumbai | Appeal No 93 | 2014 | Pending |
| The Honble High Power Committee At Mumbai | Appeal No 94 | 2014 | Pending |
| The Honble High Power Committee At Mumbai | Appeal no 95 | 2014 | Pending |
The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.
| From (declared) | To (revised) | Stated reason |
|---|---|---|
| 30 Jun 2024 | 30 Jun 2025 | The aforesaid under Construction project got delayed in the first half of year 2023 due to critical shortages of key materials like sand and ready-mix concrete, causing delays in c |
Located at Nadkarni Park, Antop Hill, Mumbai City, Mumbai City, 400037. Per the filed land record, the plot is bounded to the north by 1830 mtr wide Shaikh Mistry Road, to the south by CTS 79 and 80, to the east by 1830 mtr wide Shaikh Mistry Road and to the west by CTS 85 and 67. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.
The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.
| Landmark | Straight-line |
|---|---|
| Lower Parel / Worli business district | 4 km |
| Bandra Kurla Complex (BKC) | 5 km |
| Chhatrapati Shivaji Int'l Airport | 8 km |
| Nariman Point / Fort | 11 km |
| Powai / Hiranandani business park | 12 km |
| Andheri MIDC / SEEPZ | 12 km |
Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.
🔒 The verdict & buyer playbook · Compliance report
The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.
🔒 Unit-by-unit guidance · Unit Guidance report
Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.
🔒 Full financial records — escrow, funding & the document catalog · Compliance report
The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.
Should you buy in Sanghvi Heights Phase 2?
This page is the free MahaRERA filing summary. The full RERA Property Intelligence Report gives you the full regulatory standing, declared court litigation, buyer-complaint and adjudication history, quarterly-progress-report discipline, the builder's MahaRERA-wide track record, the building/tower breakdown, and the sanctioned layout plan. See a real one first:
Sample: Lodha Kandivali – Tower 2 → · browse all sample reports →
Compliance Report · ₹999
The regulator’s filing record, read · 1 working day
Scan with any UPI app to pay · quietlist@kotak
Unit Guidance Report · ₹2,999
Everything, down to which unit · 1 working day
Not useful to your decision? Full refund — no questions asked.
Scan with any UPI app to pay · quietlist@kotak
Paying from outside India? Pay $15 (Compliance) or $39 (Unit Guidance) via PayPal, or email hello@quietlist.in for a card invoice. Prefer to talk first, or have a portfolio to check? Same address. An information aid for your own due diligence, not legal or investment advice.
Free · Watch this project
We'll email you when this project's RERA record changes.
Sanghvi Premises Private Limited is the promoter on 5 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).
See every Sanghvi Premises Private Limited project & its RERA track record →
Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.
Last checked against the RERA register: 27 Jul 2026