Mumbai/Project record

MahaRERA · the public record

SAVERA COMPLEX

KELVE ROAD · SAVERA BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Dec 2026declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Dec 2026

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P99000016226

Delivery and registration

When is the project declared for completion?

SAVERA COMPLEX is registered with MahaRERA as P99000016226 and the promoter has declared completion for 31 Dec 2026.

31 Dec 2026

declared completion

3months to go

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP99000016226
Registered on25 Apr 2018
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today3 months to the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SAVERA COMPLEX record 33 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • QPR non-compliance — flagged by MahaRERA for not filing its mandatory quarterly progress reports.
  • Current QPR default — the promoter has stopped filing the mandatory quarterly progress report (FY 2025-2026).

Promoter record

What else is this promoter on record for?

Savera Builders Developers is the promoter of record on 5 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

5projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SAVERA COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
BUILDING NO 2 WING A1G+414 Apr 2021
BUILDING NO 2 WING B1G+414 Apr 2021
BUILDING NO 2 WING C1G+414 Apr 2021

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Dec 2026we can’t available the labours, materials and other required Essentials to Complete the Project.

Location, Land & Connectivity

Located at KELVE ROAD, KELVE ROAD, Vasai, Palghar, 401401. Per the filed land record, the plot is bounded to the north by GUT NO 193, to the south by GUT NO 43 AND 142, to the east by GUT NO 1 AND 41 and to the west by GUT NO 44. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~56 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Andheri MIDC / SEEPZ56 km
Powai / Hiranandani business park58 km
Chhatrapati Shivaji Int'l Airport60 km
Bandra Kurla Complex (BKC)63 km
Lower Parel / Worli business district70 km
Nariman Point / Fort78 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Kelve Road

Karrm Brahmaand Affordable Homes PVT LTD
Not filing quarterly progress reports · possession by Dec 2026 · Karrm Brahmaand Affordable Homes Private
Bhaskar Save Nagar
possession by Dec 2026 · Sai Builders And Developers
Rose Heights
possession by Dec 2026 · Mehandi Hasan Sarif Shalmani
THE Hill Touch
possession by Dec 2026 · Aristone Infra
SK Swarnik Homes
possession by Feb 2027 · SK Swarnik Homes
Prish Apartment
possession by Mar 2027 · Rajesh D Yadav

Other RERA-registered projects in Palghar

Savera Complex
possession by Dec 2027 · UVA Infra
Savera Heights
possession by Oct 2028 · Savera Reality
Savli Apartment
possession by Dec 2028 · Rancy Enterprises
Seabreeze Phase 1
possession by Dec 2029 · Dvnm Ventures LLP
Seasons
possession by Dec 2032 · Shiv Samarth Enterprises
Serenity Garden Wing D
declared completion Jul 2019 · Unity Estates & Developers

What to verify (QPR non-filer)

  1. Cross-check the developer's last QPR filing date on the MahaRERA portal — non-filing can indicate stalled construction.
  2. Visit the site (or request a third-party inspection report) to verify actual construction progress.
  3. If no QPR has been filed for more than two quarters, file a complaint with MahaRERA for non-disclosure.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.