SERENE CITY

Raigarh · SANGHVI BUILDTECH LLP

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

293units filed as unsoldInventory · 20 September 2026
30 Dec 2024declared completionMahaRERA registration · read 12 Jul 2026
308registered unitsMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900001738

Delivery and registration

When is the project declared for completion?

SERENE CITY is registered with MahaRERA as P51900001738 and the promoter has declared completion for 30 Dec 2024.

30 Dec 2024

declared completion

21months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900001738
Registered on29 Jul 2017
Promoter-declared completion30 Dec 2024
Current statusCertificate Signed
Against todayabout 21 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SERENE CITY record 30 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 30 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Sanghvi Buildtech Llp is the promoter of record on 48 projects registered with MahaRERA, 8 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

48projects

registered with MahaRERA

8flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

How much has actually been sold?

In SERENE CITY, 15 of 308 homes filed with MahaRERA are recorded as sold or booked (14 with registered agreements and 1 booked), about 5%, and 293 remain available.

5%sold

15 of 308 homes

₹5.30 Cr

committed by buyers

Counts and agreement value as the promoter filed them at the last compliance date; this is the filed inventory, not current availability. Of that agreement value, ₹1.81 Cr (about 34%) is recorded as collected and ₹3.49 Cr as receivable.

Source · MahaRERA sold/unsold inventory filing · read 12 Jul 2026

What buyers actually paid: across 15 registered agreements, the effective carpet rate is ₹3,860/sqft, with eight in ten falling between ₹3,741 and ₹4,262 — computed from the agreement values and carpet areas the promoter filed, not broker quotes.

No units are declared mortgaged, reserved, investor-held or not-for-sale in this inventory filing.

What the filings record, home by home

Read from MahaRERA on 20 September 2026

MahaRERA publishes, home by home, what this promoter filed: which homes are sold and which are not, the RERA carpet area of each, and for the sold ones the registered agreement value — the consideration filed for that specific home. On this project 15 homes carry one, and 293 of the 308 are recorded unsold.

Here is one of those unsold homes, priced against what buyers of the same home on other floors actually filed:

HomeCarpetFiled for the same home on other floorsBased on
A-003842 sqftRs 32.50 lakh typical, over Rs 31.50 lakh to Rs 35.88 lakh14 filed at this size

A filed consideration is what was registered for one home. It is not a valuation, and MahaRERA does not publish the date of any of these agreements — read a range as a spread, not as a trend. An unsold row means no sale had been filed for it when we looked, which is a filing state, not a promise that the home is available to you today. Only one observation of this ledger so far: no change can be reported yet.

In SERENE CITY, 70 of the 293 unsold homes have agreements filed on their own stack. The Price Comparison Report gives each of them its own row — the filed agreements behind that stack listed in full, the government reckoner value the promoter filed against it, and whether it is mortgaged to a lender while still on the unsold list. Built from the filing itself, sent by email.

See the other 292 homes — ₹2,999 →

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+1 and 308 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
SERENE CITY A-01/A-021G+12-
SERENE CITY A-03/A-041G+12-
SERENE CITY A-05/A-061G+12-
SERENE CITY A-07/A-081G+12-
SERENE CITY A-09/A-101G+12-
SERENE CITY A-11/A-121G+12-
SERENE CITY A-13/A-141G+12-
SERENE CITY A-15/A-161G+12-
SERENE CITY A-17/A-181G+12-
SERENE CITY A-19/A-201G+12-
SERENE CITY A-21/A-221G+12-
SERENE CITY A-23/A-241G+12-
SERENE CITY A-25/A-261G+12-
SERENE CITY A-27/A-281G+12-
SERENE CITY A-29/A-301G+12-
SERENE CITY A-31/A-321G+12-
SERENE CITY A-33/A-341G+12-
SERENE CITY A-35/A-361G+12-
SERENE CITY A-37/A-381G+12-
SERENE CITY A-43/A-441G+12-
SERENE CITY A-45/A-461G+12-
SERENE CITY A-47/A-481G+12-
SERENE CITY A-120/A-1211G+12-
SERENE CITY A-122/A-1231G+12-
SERENE CITY A-124/A-1251G+12-
SERENE CITY A-126/A-1271G+12-
SERENE CITY A-128/A-1291G+12-
SERENE CITY A-130/A-1311G+12-
SERENE CITY A-132/A-1331G+12-
SERENE CITY A-134/A-1351G+12-
SERENE CITY A-136/A-1371G+12-
SERENE CITY A-138/A-1391G+12-
SERENE CITY A-140/A-1411G+12-
SERENE CITY A-142/A-1431G+12-
SERENE CITY A-144/A-1451G+12-
SERENE CITY A-146/A-1471G+12-
SERENE CITY A-148/A-1491G+12-
SERENE CITY A-150/A-1511G+12-
SERENE CITY A-152/A-1531G+12-
SERENE CITY A-154/A-1551G+12-
SERENE CITY A-236/A-2371G+12-
SERENE CITY A-238/A-2391G+12-
SERENE CITY B-39/B-401G+12-
SERENE CITY B-41/B-421G+12-
SERENE CITY B-49/B-501G+12-
SERENE CITY B-53/B-541G+12-
SERENE CITY B-55/B-561G+12-
SERENE CITY B-57/B-581G+12-
SERENE CITY B-59/B-601G+12-
SERENE CITY B-61/B-621G+12-
SERENE CITY B-63/B-641G+12-
SERENE CITY B-65/B-661G+12-
SERENE CITY B-67/B-681G+12-
SERENE CITY B-70/B-711G+12-
SERENE CITY B-72/B-731G+12-
SERENE CITY B-74/B-751G+12-
SERENE CITY B-76/B-771G+12-
SERENE CITY B-78/B-791G+12-
SERENE CITY B-80/B-811G+12-
SERENE CITY B-82/B-831G+12-
SERENE CITY B-84/B-851G+12-
SERENE CITY B-86/B-871G+12-
SERENE CITY B-88/B-891G+12-
SERENE CITY B-90/B-911G+12-
SERENE CITY B-92/B-931G+12-
SERENE CITY B-94/B-951G+12-
SERENE CITY BUILDING-1, C-96 TO C-1191G+12-
SERENE CITY BUILDING-2, C-156 TO C-1791G+12-
SERENE CITY BUILDING-5, C-212 TO C-2351G+12-
SERENE CITY BUILDING-6, C240 TO C2631G+1134-
SERENE CITY BUILDING-7, C-264 TO C-2871G+12-
SERENE CITY BUILDING-8, C-288 TO C-3111G+12-
SERENE CITY BUILDING-4, D-196 TO D-2111G+130-
SERENE CITY BUILDING-3, D-180 TO D-1951G+12-

Unit mix on the filing: 308 residential.

Legal and disputes

What disputes are disclosed?

1 complaint is on the MahaRERA record for SERENE CITY, with orders passed in 0 of them.

1complaint

0with an order

Counts as disclosed in the project record.

Source · MahaRERA project disclosures · read 12 Jul 2026

Complaint no.FiledPartiesStatus
CC1250289418/08/2025Jignesh Thaker vs SANGHVI BUILDTECH LLPpending / no order on file

Legal & Litigation

The promoter has declared 2 court cases on this project to MahaRERA. Litigation can cloud the land title or stall the build — have a lawyer pull the cause list for each and confirm whether it touches the title to your home. This is declared by the promoter; there may be further cases not on the RERA record.

CourtCase no.YearStatus
Civil Judge Senior Division At Panvel Court892009Framing Issues
Civil Judge Senior Division At Panvel912009For Framing Issues

Location, Land & Connectivity

Located at Survey No 62, Karjat, Raigarh, 400086. Per the filed land record, the plot is bounded to the north by S NO 50-1F, to the south by FOREST, to the east by S NO 44-1A and to the west by S NO 42-5. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~3 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Powai / Hiranandani business park3 km
Chhatrapati Shivaji Int'l Airport4 km
Bandra Kurla Complex (BKC)5 km
Andheri MIDC / SEEPZ6 km
Lower Parel / Worli business district13 km
Nariman Point / Fort20 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar West

O AND S Royale
possession by Dec 2026 · Suchita Orange Project Royale
Sarvonnati CHS LTD
Deregistered by MahaRERA · possession by Dec 2026 · JAI Enterprises
Vighneshwar Cooperative Housing Society Limited
possession by Dec 2026 · Vighneshwar Coop Housing Society Limited
Arihant Heights
possession by Dec 2026 · Arihant Infrastructure Company
Avani Signature
possession by Dec 2026 · Avani Buildcon
Sanghvi Parsssva Jivdaya
possession by Dec 2026 · Sanghvi Constructions

Other RERA-registered projects in Mumbai City

Sesen
possession by Dec 2027 · Sesen Realty PVT LTD
Seven Dhuleva
possession by Dec 2027 · Dhuleva Infrastructures LLP
Seventh Avenue
possession by Dec 2026 · Rubberwala Housing & Infradevelopmen
Shaanti Ashish
declared completion Dec 2022 · Ruparel Estates India Pvt Ltd
Shahid Nagar
possession by Dec 2027 · Neumec AND Sangam JV
Shakuntala Heights
possession by Dec 2030 · D R Properties

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026