MahaRERA Property Intelligence · Raigarh

SHAGUN PRESTIGE

P52000016613 · NERAL · promoter Shagun Reals

Certificate SignedDue 01 Dec 2025

Delivery & Registration

MahaRERA registrationP52000016613
Registered on25 May 2018
Promoter-declared completion01 Dec 2025
Current statusCertificate Signed
Against todayabout 7 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Builder Track Record

Across MahaRERA, Shagun Reals is the promoter of record on 35 projects, of which 2 carry a MahaRERA regulator flag (insolvency, deregistration, completion-lapse or QPR default). Read the pattern across the portfolio, not just this project's brochure — matched on the promoter name in the MahaRERA register.

Sales & Inventory

Of 22 homes filed with MahaRERA, 18 are sold/booked and 4 remain available (~82% sold) — selling steadily. Buyers have committed ₹3.84 Cr in agreement value so far. Of that, ₹3.13 Cr (~82%) is already collected, ₹73.56 Lakh receivable — a read on how far along these sales really are. Note: the project registers 32 homes in total, but this sold/unsold inventory filing covers only 22 of them — the other 10 aren't in the ledger yet. Ask the builder what they are (an unreleased phase, held-back stock, or non-saleable/car-park units) before reading too much into the percentage. This is the promoter's own reported inventory as at the last compliance filing; confirm current availability directly.

What buyers actually paid: across 18 registered agreements, the effective carpet rate is ₹6,679/sqft (typical range ₹5,360–₹7,507) — computed from the agreement values and carpet areas the promoter filed, not broker quotes. Compare your quote against this before negotiating.

The unsold units on the filing — if you're quoted a unit NOT on this list, ask why it shows as sold/booked on the RERA record:

FloorUnitCarpetReckoner value
Floor 1R2-A 103209 sqft (19.43 sqm)₹7.81 Lakh
Floor 2R2-A 203209 sqft (19.43 sqm)₹7.81 Lakh
Floor 4R1-401396 sqft (36.83 sqm)₹14.81 Lakh
Floor 4R2-A 404284 sqft (26.43 sqm)₹10.62 Lakh

⚠ The inventory filing also declares: 2 reserved and 8 not for sale. Before booking, confirm YOUR unit appears in none of these lists and get any lender NOC in writing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+5 and 32 homes are registered across the project.

BuildingWingsFloorsHomesDeclared completion
R31G+5--
R21G+521-
R11G+49-
BUNGLOW1G+12-

Unit mix on the filing: 32 residential.

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
30 Mar 202201 Dec 2025We have total 3 Building name of R1, R2 & R3 We have obtained a Commencement Certificate of all buildings now we had completed Construction work of R3 Building and Received Occupat

Location, Land & Connectivity

Located at NERAL, NERAL DHAMOTE, Karjat, Raigarh, 421101. Per the filed land record, the plot is bounded to the north by ROAD, to the south by OPEN PLOT, to the east by OPEN PLOT and to the west by MARUTI CHANCHE HOUSE. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~45 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park45 km
Bandra Kurla Complex (BKC)48 km
Chhatrapati Shivaji Int'l Airport49 km
Andheri MIDC / SEEPZ49 km
Lower Parel / Worli business district52 km
Nariman Point / Fort53 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Padghe

Jash Apartment
possession by Dec 2027 · Shri SAI Construction
Pushpanjali
possession by Dec 2034 · Ramlal Shankarlal Jat

Other RERA-registered projects in Raigarh

Shah Arcade
declared completion Jul 2022 · S.g.enterprises
Shah Kingdom IV Phase D Wing
possession by Dec 2027 · Shah Group Builders LTD
Shah Kingdom Phase II B Wing
possession by Dec 2029 · Shah Group Builders LTD
Shah Kingdom Phase III C Wing Shops AND Podiums
possession by Dec 2027 · Shah Group Builders LTD
Shah Kingdom Phase V E Wing
possession by Dec 2027 · Shah Group Builders LTD
Shakti
declared completion Dec 2018 · Parag Pankaj Thakker

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026