MahaRERA Property Intelligence · Thane

Shankar Heights, Phase 3

P51700010807 · promoter Laxmi Kamal Associates

Certificate SignedDue 30 Dec 2018

Delivery & Registration

MahaRERA registrationP51700010807
Registered on31 Aug 2017
Promoter-declared completion30 Dec 2018
Current statusCertificate Signed
Against todayabout 91 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
Manali1G+830 Dec 2018
Bluebell1G+830 Dec 2018
Nidhi A Wing1G+830 Dec 2018
Nidhi B Wing1G+830 Dec 2018

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at Ambarnath, Thane, 421505. Per the filed land record, the plot is bounded to the north by Shankar Heights Phase 4, to the south by Shankar Heights Phase 2, to the east by Open Area and to the west by Govt Reserved Garden Area. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~33 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park33 km
Andheri MIDC / SEEPZ36 km
Chhatrapati Shivaji Int'l Airport38 km
Bandra Kurla Complex (BKC)39 km
Lower Parel / Worli business district46 km
Nariman Point / Fort51 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Laxmi Kamal Associates is the promoter on 6 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Laxmi Kamal Associates

Laxmi Kamal Associates
FlaggedThane
Laxmi Kamal Associates
FlaggedThane
Laxmi Kamal Associates
FlaggedThane
Laxmi Kamal Associates
FlaggedThane
Laxmi Kamal Associates
FlaggedThane

Other RERA-registered projects in Ambernath

Vishwajeet Paradise
possession by Dec 2026 · Vishwajeet Meadows
Shankar Heights Phase 5
possession by Dec 2026 · Laxmi Kamal Associates
Nidhi Residency
possession by Mar 2027 · Aditya Yash Builders
Shreeji Landmark Phase 1
possession by Mar 2027 · Deep Laxmi Associates
Daisy Gardens Building No.13
possession by Jun 2027 · Ankita Builders
Daisy Gardens Survey NO 12 Phase I
possession by Jun 2027 · Ankita Builders

Major developers building in Ambernath

Other RERA-registered projects in Thane

Shankar Heights Phase 4
declared completion Jun 2022 · Laxmi Kamal Associates
Shankar Heights Phase 5
possession by Dec 2026 · Laxmi Kamal Associates
Shankar Heights Phase 6
possession by Dec 2028 · Laxmi Kamal Associates
Shankar Palace
declared completion Oct 2023 · Shree Ramesh Homes Builders And Develope
Shankar Prasad Paradise
declared completion Oct 2025 · Kelkar Lele AND Associates
Shankeshwar Darshan
possession by Dec 2029 · Kalpvriksh Homes LLP

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026