Mumbai/Project record

MahaRERA · the public record

Shanti Solitaire

Thane · Marvel Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2019declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2019

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51900003463

Delivery and registration

When is the project declared for completion?

Shanti Solitaire is registered with MahaRERA as P51900003463 and the promoter has declared completion for 31 Mar 2019.

31 Mar 2019

declared completion

90months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51900003463
Registered on05 Aug 2017
Promoter-declared completion31 Mar 2019
Current statusCertificate Signed
Against todayabout 90 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shanti Solitaire record 7 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 7 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Marvel Developers is the promoter of record on 53 projects registered with MahaRERA, 31 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

53projects

registered with MahaRERA

31flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shanti Solitaire in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Shanti Soletaire1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2019The status of "Shanti Solitaire" project is that we have completed the building with finishing work . However, due to delay in completion of puzzle parking and car lift by the cont

Location, Land & Connectivity

Located at Thane, Thane, 400077. Per the filed land record, the plot is bounded to the north by 30 ft Road, to the south by Plot No 80, to the east by 60 ft Road and to the west by Plot No 82. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Bandra Kurla Complex (BKC)4 km
Chhatrapati Shivaji Int'l Airport4 km
Powai / Hiranandani business park4 km
Andheri MIDC / SEEPZ7 km
Lower Parel / Worli business district12 km
Nariman Point / Fort19 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Ghatkopar East

Hema Apartments CO-Operative Housing Society Limited
possession by Sep 2026 · Hema Appartments CO-Operative Housing So
Centrona ZEN-A
possession by Dec 2026 · Elevated Avenue Realty LLP
Centrona ZEN-B
possession by Dec 2026 · Elevated Avenue Realty LLP
Centrona Zest- A
possession by Dec 2026 · Elevated Avenue Realty LLP
Centrona Zest- B
possession by Dec 2026 · Elevated Avenue Realty LLP
Ruparel Pristine
possession by Dec 2026 · Shiddhivinayak Developers

Major developers building in Ghatkopar East

Other RERA-registered projects in Mumbai City

Shanti Square
possession by Dec 2029 · Shanti Siddhi Realtors LLP
Shapoorji Pallonji The Odyssey 1
possession by Aug 2031 · Floreat Investments Private Limited
Shayona
possession by Dec 2026 · Devesh Narendra Jani
Sheetal Sapphire
possession by Dec 2030 · Sheetal Developers
Shelaji Avenues
possession by Dec 2026 · Ashirwad Shelaji Developers LLP
Shilp Serenity
possession by Dec 2027 · Sheela Shilpakar LLP

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026