Mumbai/Project record

MahaRERA · the public record

SHIV SAI KRUPA CHS LTD

AMBERNATH · P G BUILDERS & DEVELOPERS

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Jun 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Jun 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51700029095

Delivery and registration

When is the project declared for completion?

SHIV SAI KRUPA CHS LTD is registered with MahaRERA as P51700029095 and the promoter has declared completion for 30 Jun 2024.

30 Jun 2024

declared completion

27months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51700029095
Registered on26 Apr 2021
Promoter-declared completion30 Jun 2024
Current statusCertificate Signed
Against todayabout 27 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHIV SAI KRUPA CHS LTD record 13 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 13 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHIV SAI KRUPA CHS LTD in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+8.

BuildingWingsFloorsDeclared completion
SHIV SAI KRUPA CHS LTD1G+830 Jun 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at AMBERNATH, VADAVALI, Ambarnath, Thane, 421501. Per the filed land record, the plot is bounded to the north by CTS NO 8720, to the south by CTS NO 8718, to the east by CTS NO 6653 and to the west by ROAD. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

P G Builders & Developers is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

See every P G Builders & Developers project & its RERA track record →

Other RERA-registered projects in Ambernath

Ashok Smruti
possession by Sep 2026 · Asha Construction
Chadha Residency
possession by Sep 2026 · Chadha Developers AND Promoters
Dalals Square
possession by Sep 2026 · Dalal Realty
GNP Galaxy Phase - III
possession by Sep 2026 · Roshni Enterprises
Meera Nanda Bliss
possession by Nov 2026 · Meera Homes LLP
Raj Residency
possession by Nov 2026 · Vijay Chahu Patil

Major developers building in Ambernath

Other RERA-registered projects in Thane

Shiv SAI Residency
declared completion Oct 2025 · SAI Deep Developers
Shiv Samruddhi
possession by Mar 2027 · Hari Infrastructure
Shiv Sarovar
declared completion May 2025 · Mahesh Bharat Divnale
Shiv Sarovar Heritage
possession by Dec 2030 · SAI Shrushti Enterprises
Shiv Sarovar Wing B
declared completion May 2026 · Mahesh Bharat Divnale
Shiv Savli Complex J Wing
declared completion Dec 2024 · Aadesh Builders AND Developers

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026