Mumbai/Project record

MahaRERA · the public record

SHRADDHA AVENUE

goregaon West · ANIL MEGHARAJ WADHARE

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Jul 2023declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Jul 2023

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800008942

Delivery and registration

When is the project declared for completion?

SHRADDHA AVENUE is registered with MahaRERA as P51800008942 and the promoter has declared completion for 31 Jul 2023.

31 Jul 2023

declared completion

38months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800008942
Registered on19 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 38 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRADDHA AVENUE record 25 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 25 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Anil Megharaj Wadhare is the promoter of record on 2 projects registered with MahaRERA, 1 of which carries a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

2projects

registered with MahaRERA

1flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRADDHA AVENUE in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
SHRADDHA AVENUE1G+14-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at goregaon West, M G Road, Andheri, Mumbai Suburban, 400062. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by EXISTING ROAD, to the east by Existing Slum and to the west by Proposed DP Road. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district18 km
Nariman Point / Fort26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anil Megharaj Wadhare is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other flagged projects by Anil Megharaj Wadhare

Anil Megharaj Wadhare
FlaggedMumbai Suburban

Other RERA-registered projects in Goregaon West

Modirealty Vatvriksh
possession by Sep 2026 · Modirealty Developers PVT LTD
Devtaa Pratham
possession by Dec 2026 · Vipul Mitra CO-Operative Housing Society
Manju Villa
possession by Dec 2026 · Meghna Developers AOP
Nirlon Employees CHS LTD Building NO. 10
possession by Dec 2026 · Shivam Parivar Developers Private Limite
Happy Home Enclave
possession by Dec 2026 · JD & FC Ventures LLP
Navkar Ashray
Not filing quarterly progress reports · possession by Dec 2026 · Navkar Builder & Devvelopers

Other RERA-registered projects in Mumbai Suburban

Shraddha CHS Adityaraj Anchor
possession by Mar 2027 · Adityaraj Builders
Shraddha Classic
possession by Jun 2027 · Shraddha Landmark Private Limited
Shraddha Elite
declared completion Dec 2025 · Shraddha Developers & Realtors
Shraddha Evoque
declared completion Aug 2026 · Shraddha Landmark Private Limited
Shraddha Gold Crest
possession by Dec 2027 · Shree Krishna Rahul Developers
Shraddha Imperia
possession by May 2028 · Shraddha Landmark Private Limited

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026