MahaRERA Property Intelligence · Mumbai Suburban

SHRADDHA AVENUE

P51800008942 · goregaon West · promoter Anil Megharaj Wadhare

Certificate SignedDue 31 Jul 2023

Delivery & Registration

MahaRERA registrationP51800008942
Registered on19 Aug 2017
Promoter-declared completion31 Jul 2023
Current statusCertificate Signed
Against todayabout 36 months past the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+14.

BuildingWingsFloorsDeclared completion
SHRADDHA AVENUE1G+14-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Location, Land & Connectivity

Located at goregaon West, M G Road, Andheri, Mumbai Suburban, 400062. Per the filed land record, the plot is bounded to the north by D P ROAD, to the south by EXISTING ROAD, to the east by Existing Slum and to the west by Proposed DP Road. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

Location & connectivity

The nearest major job hub is ~4 km away — a manageable everyday commute to a major job hub.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Powai / Hiranandani business park8 km
Chhatrapati Shivaji Int'l Airport8 km
Bandra Kurla Complex (BKC)11 km
Lower Parel / Worli business district18 km
Nariman Point / Fort26 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Anil Megharaj Wadhare is the promoter on 2 MahaRERA-registered projects, of which 1 carry a regulator flag (insolvency, deregistration, suspension, completion lapse or QPR default). A pattern across a builder's portfolio matters more than any one project's brochure — look into these before you trust this registration:

Other RERA-registered projects in Goregaon West

Modirealty Vatvriksh
possession by Sep 2026 · Modirealty Developers PVT LTD
Devtaa Pratham
possession by Dec 2026 · Vipul Mitra CO-Operative Housing Society
Manju Villa
possession by Dec 2026 · Meghna Developers AOP
Nirlon Employees CHS LTD Building NO. 10
possession by Dec 2026 · Shivam Parivar Developers Private Limite
Happy Home Enclave
possession by Dec 2026 · JD & FC Ventures LLP
Laxmi Leela Arhum
possession by Dec 2026 · Laxmi Leela Constructions LLP

Major developers building in Goregaon West

Other RERA-registered projects in Mumbai Suburban

Shraddha Chhaya
declared completion Mar 2023 · Shraddha Chhaya Developers LLP
Shraddha CHS Adityaraj Anchor
possession by Mar 2027 · Adityaraj Builders
Shraddha Classic
possession by Jun 2027 · Shraddha Landmark Private Limited
Shraddha Elite
declared completion Dec 2025 · Shraddha Developers & Realtors
Shraddha Evoque
possession by Aug 2026 · Shraddha Landmark Private Limited
Shraddha Gold Crest
possession by Dec 2027 · Shree Krishna Rahul Developers

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026