Mumbai/Project record

MahaRERA · the public record

SHRADDHA WOODS

Amboli · Touchwood Developers

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

31 Mar 2024declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

31 Mar 2024

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P51800002932

Delivery and registration

When is the project declared for completion?

SHRADDHA WOODS is registered with MahaRERA as P51800002932 and the promoter has declared completion for 31 Mar 2024.

31 Mar 2024

declared completion

30months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP51800002932
Registered on04 Aug 2017
Promoter-declared completion31 Mar 2024
Current statusCertificate Signed
Against todayabout 30 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHRADDHA WOODS record 27 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 27 quarterly progress reports on record since registration, with no current default.

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHRADDHA WOODS in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+13.

BuildingWingsFloorsDeclared completion
Wing A1G+831 Dec 2021
Wing B1G+13-

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 1 time, as recorded on the register.

FromExtended toStated reason
as registered31 Mar 2024The project was taken over by us from the original developer due to their financial inability to complete the project. However, after taking over, we had to face the challenges lik

Location, Land & Connectivity

Located at Amboli, Off Cessar Road, Ward GSouth, Mumbai City, 400102. Per the filed land record, the plot is bounded to the north by 491A, to the south by 507, to the east by 506 and to the west by 490. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~4 km away — walking/short-hop distance to a major employment hub — a genuine work-near-home location.

LandmarkStraight-line
Andheri MIDC / SEEPZ4 km
Chhatrapati Shivaji Int'l Airport7 km
Powai / Hiranandani business park8 km
Bandra Kurla Complex (BKC)9 km
Lower Parel / Worli business district16 km
Nariman Point / Fort24 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Jogeshwari West

Aksa Tower
possession by Sep 2026 · HFI Industries
GSA Grandeur
Past its declared completion date · possession by Oct 2026 · G S A Constructions
Lashkaria Pearl
possession by Nov 2026 · Lashkaria Housing & Infrastructure P
A H Avenue
possession by Dec 2026 · A.h. Constructions
KEY Tech Park
possession by Dec 2026 · M/s Keytech
Universal Garden- B Wing
possession by Dec 2026 · Pagarani Universal Infrastructure Pvt Lt

Major developers building in Jogeshwari West

Other RERA-registered projects in Mumbai Suburban

Shradha Residency
declared completion Jun 2026 · Konark Shradha Realtors
Shree
possession by Dec 2028 · JYD Infra PVT LTD
Shree Abhishek CHS Ltd Wing C
declared completion May 2025 · Divya Enterprise
Shree Ashish Apartment CO-Operative Housing Society Limited
possession by Jun 2030 · OM SAI Developers & Promoters
Shree Balaji 7
possession by Sep 2026 · Saptrishi Landmarks LLP
Shree Balaji Avenue
possession by Dec 2026 · Shree Balaji & CO

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026