Mumbai/Project record

MahaRERA · the public record

Shramik Vaibhav

Shedung · Ajay Constructions

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

29 May 2022declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

29 May 2022

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000010831

Delivery and registration

When is the project declared for completion?

Shramik Vaibhav is registered with MahaRERA as P52000010831 and the promoter has declared completion for 29 May 2022.

29 May 2022

declared completion

52months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000010831
Registered on31 Aug 2017
Promoter-declared completion29 May 2022
Current statusCertificate Signed
Against todayabout 52 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for Shramik Vaibhav record 20 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Completion date lapsed — the registered completion date has lapsed without a recorded finish.
  • Filing progress reports — 20 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Ajay Constructions is the promoter of record on 64 projects registered with MahaRERA, 15 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

64projects

registered with MahaRERA

15flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for Shramik Vaibhav in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
Building 11G+431 May 2019
Building 21G+431 May 2019

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Deadline Extensions

The MahaRERA completion deadline for this project has been formally extended 2 times, as recorded on the register.

FromExtended toStated reason
as registered30 May 2020• The structure for the proposed Project along with brickwork has been completed as per the earlier sanction and Commencement certificate. • The approvals for additional area decl
30 May 202029 Nov 2021That there was delay in revised approvals for additional area and therefore the construction work could not be carried out for the additional area declared at the time of registrat

Location, Land & Connectivity

Located at Shedung, Off. National Highway 4, Thane, Thane, 410206. Per the filed land record, the plot is bounded to the north by Gat no 110 pt, to the south by Gaothan, to the east by Gat no 123 and to the west by Gat no 110 pt. These are the boundaries as recorded in the filed land record.

Location & connectivity

The nearest major job hub is ~34 km away — well outside the job hubs — this is a value/space play, not a short-commute one; budget for the drive.

LandmarkStraight-line
Powai / Hiranandani business park34 km
Bandra Kurla Complex (BKC)35 km
Chhatrapati Shivaji Int'l Airport36 km
Lower Parel / Worli business district37 km
Nariman Point / Fort37 km
Andheri MIDC / SEEPZ38 km

Straight-line distances from the geocoded project locality (the RERA address is an area, not a door) — directional, not door-to-door drive times. Check the actual road route, the nearest metro station and daily-need shops/schools/hospitals on a site visit.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Panvel

Arihant Clan Aalishan Phase I
possession by Sep 2026 · Arihant Vatika Realty Private Limited
Balaji Heritage
possession by Sep 2026 · Buildfox Realty LLP
Delta Hills
possession by Sep 2026 · Shree Ganesh Enterprises
Delta Riviera
possession by Sep 2026 · Shreenathji Organisers Pvt. Ltd.
GAJ Oasis
possession by Sep 2026 · Shiv Builders AND Developers
Green View
possession by Sep 2026 · Siddhivinayak Developers

Major developers building in Panvel

Other RERA-registered projects in Raigarh

Shravan Apartment
declared completion Mar 2023 · Harikrishna Infra
Shravan Siddhant
possession by Dec 2030 · Shree Samarth Krupa Builders & Developer
Shree Aangan - A Wing
possession by Dec 2027 · Shiv Creators LLP
Shree Ambika Aangan
declared completion Jun 2023 · Lumbaram Modaram Patel
Shree Apartment
possession by Dec 2028 · Not Available
Shree Apartment
declared completion Dec 2022 · Shree Siddhivinayak Builders AND Develop

What to do next (past deadline)

  1. Ask the developer for the RERA extension filing — they must file for an extension before the deadline passes.
  2. Check the MahaRERA portal for a revised completion date or extension order.
  3. Review your allotment letter's possession clause for interest or compensation terms on delayed handover.
  4. File a complaint with MahaRERA if no extension has been filed and the delay is impacting possession.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 20 Sep 2026