Mumbai/Project record

MahaRERA · the public record

SHREE EKDANT COMPLEX

PALI · YOGESH KANTILAL SHAH

Know the project.
Then choose your home.

The registration, progress and filed details in one place. Go further with an independent reading of the project’s evidence.

30 Dec 2021declared completionMahaRERA registration · read 12 Jul 2026
Certificate Signedregistration statusMahaRERA registration · read 12 Jul 2026

The record · free to read

Registration read 12 Jul 2026

Progress & dates

The timeline on file.

Available record

No construction trend to plot.

The records used for this page do not supply a series of construction percentages. This does not establish whether possession has been given.

declared completion

30 Dec 2021

The registered date and a construction update answer different questions. Neither is a confirmation of possession.

MahaRERA registration · read 12 Jul 2026

From another project

See the report before you buy.

A published sample shows the level of detail, source illustrations and buyer reasoning. Its findings belong to that project.

Read a sample report ↗

The source record

The details behind the headline.

MahaRERA · P52000017576

Delivery and registration

When is the project declared for completion?

SHREE EKDANT COMPLEX is registered with MahaRERA as P52000017576 and the promoter has declared completion for 30 Dec 2021.

30 Dec 2021

declared completion

57months past

against the declared date

The completion date and status as they stand on the MahaRERA registration record.

Source · MahaRERA project registration · read 12 Jul 2026

MahaRERA registrationP52000017576
Registered on28 Aug 2018
Promoter-declared completion30 Dec 2021
Current statusCertificate Signed
Against todayabout 57 months past the declared date

Approvals and compliance

What compliance filings are on record?

MahaRERA's defaulter and deregistration lists and the quarterly-progress filing for SHREE EKDANT COMPLEX record 14 quarterly progress reports since registration.

Entries as they appear on MahaRERA's own lists and the project's progress filing.

Source · MahaRERA defaulter, deregistration and QPR lists · read 12 Jul 2026

  • Filing progress reports — 14 quarterly progress reports on record since registration, with no current default.

Promoter record

What else is this promoter on record for?

Yogesh Kantilal Shah is the promoter of record on 24 projects registered with MahaRERA, 2 of which carry a MahaRERA regulator flag (insolvency, deregistration, completion lapse or QPR default).

24projects

registered with MahaRERA

2flagged

by MahaRERA

Counted across Quietlist's full MahaRERA register store, matched on the promoter name as it appears on each filing.

Source · MahaRERA register, all projects · read 12 Jul 2026

Sales

Are registered sale-agreement prices available?

No registered sale-agreement price is recorded for SHREE EKDANT COMPLEX in the MahaRERA project file.

Not available

This is what the record does not contain, not a value of zero.

Source · MahaRERA project file · checked 12 Jul 2026

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+4.

BuildingWingsFloorsDeclared completion
SHREE EKDANT COMPLEX1G+431 Dec 2020

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading.

Location, Land & Connectivity

Located at PALI, SUDHAGAD, Khalapur, Raigarh, 410205. Per the filed land record, the plot is bounded to the north by 54 NO, to the south by PROPOSED 9 M W ROAD, to the east by CTS NO 1872-1-1 and to the west by CTS 1872-3. These are the boundaries as recorded in the filed land record.

Free · Watch this project

We'll email you when this project's RERA record changes, and send the 14-point booking checklist with the first email.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Builder track record

Yogesh Kantilal Shah is the promoter on 2 MahaRERA-registered projects, with none currently carrying a regulator flag — a reassuring wider track record (matched on the promoter name in the register; it doesn't guarantee this specific project, but a clean portfolio is a good sign).

Other flagged projects by Yogesh Kantilal Shah

Yogesh Kantilal Shah
FlaggedRaigarh

Other RERA-registered projects in Pali

Shubham Residency
possession by Oct 2026 · G D Jain Infra Projects
Annaprabha Complex
possession by Dec 2026 · Kishor Prabhakar Dandekar
City Of Music Phase III
possession by Dec 2026 · Nirvana Leisure Realty
City OF Music Phase IV
possession by Dec 2026 · Nirvana Leisure Realty
Joy Villa Phase-I
possession by Dec 2026 · Sadanand Laxmanrao Patil
Kenisha Resort Residences
possession by Dec 2026 · Kpin Real Estate Ventures

Other RERA-registered projects in Raigarh

Shree Ekdanta Residency
possession by Dec 2026 · Milestone Construction
Shree Empire
possession by Dec 2027 · Shree Builders & Developers
Shree Empire Plaza
possession by Dec 2030 · Shree Enterprises
Shree G Funzone
declared completion Dec 2023 · Rajesh Amarlal Thakur
Shree G Square
declared completion Dec 2019 · Rajesh Amarlal Thakur
Shree Gajanan Apartment
declared completion Dec 2022 · Gajanan Rama Naik

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 11 Sep 2026