MahaRERA Property Intelligence · Thane

SHREE KRISHNA DHAM

P51700055615 · BHAYANDAR · promoter Sawariya Construction Co

Certificate SignedDue 31 Dec 2026

Delivery & Registration

MahaRERA registrationP51700055615
Registered on04 Apr 2024
Promoter-declared completion31 Dec 2026
Current statusCertificate Signed
Against today5 months to the declared date

Regulatory Standing

MahaRERA's own defaulter/deregistration lists and the project's quarterly-progress-report filing — the regulator's view of whether this project is in good standing.

Buildings & Wings

The buildings and wings registered under this project, with each tower's sanctioned height and declared completion date. Here the tallest tower rises to G+7.

BuildingWingsFloorsDeclared completion
SHREE KRISHNA DHAM1G+731 Dec 2024

Complaints

No buyer complaints were on this project's MahaRERA record at the time of reading — a clean sheet worth re-checking near booking.

Deadline Extensions

The promoter has had the MahaRERA completion deadline formally extended 1 time. Each extension is the regulator letting the finish line move — the clearest evidence of delivery slippage, straight from the record.

From (declared)To (revised)Stated reason
31 Dec 202431 Dec 2026That we had registered the aforesaid project on 04.04.2024 and validity period of the project was for only Nine months. We were new and our consultant did not guide us about the pr

Location, Land & Connectivity

Located at BHAYANDAR, RAM MADNIR ROAD, Thane, Thane, 401101. Per the filed land record, the plot is bounded to the north by UMA GOVIND BLDG, to the south by YASH DATT BUNGLOW, to the east by EKVEERA TOWER and to the west by GAJANAN BHAVAN. Confirm these against the 7/12 extract and the sanctioned plan before you rely on them.

🔒 The verdict & buyer playbook · Compliance report

The paid report opens with the overall risk read on this MahaRERA filing, exactly what I'd do as a buyer in this project, who it suits, and the questions to put to the promoter before you commit.

Unlock in the ₹999 report →

🔒 Unit-by-unit guidance · Unit Guidance report

Which building/wing and unit to prefer and the sanctioned-plan read for this project — the ₹2,999 guidance layer.

Unlock in the ₹2,999 report →

🔒 Full financial records — escrow, funding & the document catalog · Compliance report

The RERA 70% designated-escrow account activity, the declared means-of-finance, the professionals of record, and every document filed with MahaRERA — the raw records the read above is built on.

Unlock in the ₹999 report →

Free · Watch this project

We'll email you when this project's RERA record changes.

Something went wrong — email hello@quietlist.in.

✓ You're watching — we'll email you if the RERA record changes.

Other RERA-registered projects in Bhayander West

Anantsavitri Ratna Heights
possession by Aug 2026 · Krisha Realty
Bhairav Enclave
possession by Aug 2026 · Leena Estate Venture
Mukundam
possession by Aug 2026 · Shree Ramjeevdani Realtors
Saroj Chandra Krupa
possession by Oct 2026 · S C Associates
SAI Hanuman Tower
possession by Dec 2026 · Shree Samartha Developers
Chandanbala
possession by Dec 2026 · Hemant Sagarmal Jain

Other RERA-registered projects in Thane

Shree Krishna Heights
declared completion Dec 2025 · Nandini Builders & Developers
Shree Krishna Infra
declared completion Apr 2026 · Shree Krishna Infra
Shree Krishna Kunj
declared completion May 2026 · Bhagwati Builders AND Developers
Shree Krishna Kunj CO-OP HSG SOC LTD
possession by Dec 2026 · Infinity Infra
Shree Krishna Paradise
declared completion Dec 2022 · RAM Associates
Shree Krishna Plaza
declared completion Dec 2019 · Shree Hanuman Enterprises

What to verify before you book

  1. Confirm the MahaRERA registration is live and read the project page on the MahaRERA portal for the sanctioned plan, approvals and the promoter's quarterly progress reports.
  2. Check the declared completion date against actual site progress — registration is not the same as a delivered, occupancy-certified building.
  3. Verify the exact carpet area, floor and unit number in your agreement match the sanctioned plan (not the brochure's saleable area).
  4. Confirm the title, the 7/12 land extract and that your payments go to the project's designated RERA escrow account.

Flags are from MahaRERA's own published problem lists — not a claim about the developer's intent. Explore every flagged project on our Mumbai, Thane & the MMR RERA red-flag register.

Last checked against the RERA register: 27 Jul 2026